| 1996 |
| Stormwater Management Master Plan adopted |
| Stormwater Management Design Criteria adopted |
| Stormwater Engineer added to staff |
| Development and engineering standards implemented |
| 1997 |
| Capital improvement projects started |
| Account Clerk II added to staff |
| Stormwater utility fees and billing system established at 2$ per ERU |
| Field Supervisor added to staff, Stormwater Maintenance Crew created |
| Senior Maintenance Worker and (2) Maintenance Worker I added to staff |
| 1998 |
| Administrative Policy on Stormwater Maintenance established |
| Senior Maintenance Worker added to staff |
| Storm sewer construction standards revised |
| Carolina Street capital improvement project completed |
| 1999 |
| 3rd and Michigan capital improvement project completed |
| Swimming Pool Discharge Regulations adopted |
| "No Dumping" markers placed on curb inlets by volunteer groups |
| 9th and Vermont capital improvment project completed |
| 29th Court capital improvement project completed |
| 2000 |
| Stormwater Engineering Inspector added to staff |
| Stormwater Utility Update published |
| Drainage easement mapping and enforcement established |
| 8th and New York tunnel replacement project completed |
| Stormwater Utility rate study completed, fee increases established |
| 2001 |
| Stormwater fees increased to 3$ per ERU |
| Stormwater Utility Web page launched |
| Stormwater Pollution Prevention Ordinance adopted and implemented |
| Construction site erosion control methods initiated |
| 2002 |
| Maintenance Worker II added to staff |
| 21st Stewart to Naismith capital improvement project completed |
| Stormwater Quality Technician added to staff |
| Pollutant discharge detection and elimination program established |
| 2003 |
| Stormwater fees increased to 4$ per ERU |
| NPDES permit application prepared for March 2003 EPA deadline |
| Increase public education on stormwater pollution |
| 2004 |
| Increase enforcement of stormwater pollution prevention |
| 21st and Massachusetts capital improvement project completed |
| 2005 |
| 13th and Oregon capital improvement project completed |
| Ridge Court capital improvement project completed |
| North Lawrence Drainage Study completed |
| 2006 |
| Hired new Stormwater Engineer (filled vacancy) |
| Letter of Map Revision completed by FEMA for 19th and Learnard Avenue project |
| Letter of Map Revision completed by FEMA for 13th and Orgegon project |