INDEX
Page
EXECUTIVE SUMMARY
2
EXISTING CONDITIONS
...........
4
Existing Right-of-Way/Easements
4
Geotechnical
Investigation
5
Utilities
..
6
PRELIMINARY DESIGN
9
Traffic
Analysis
..
9
Pavement
Design
12
Typical
Sections
..
14
Traffic
Signal Analysis
. 17
Storm
Sewer Analysis
..
18
OPTION 1 REMOVE & REPLACE EXISTING
PAVEMENT
20
OPTION 2 PREFERRED PROFILE ALIGNMENT (10%
GRADE)
22
OPTION 3 PREFERRED PROFILE ALIGNMENT (8%
GRADE)
..
25
OPTION 4 PARTIAL PREFERRED PROFILE (10%
GRADE)
28
CONSTRUCTION ISSUES
.
31
Construction
Sequencing
..
31
Construction
Schedule Issues
.. 33
RECOMMENDATION
34
FIGURES
Figure
A Existing Conditions Plan View
Figure
B Proposed Lane Configurations
Figure C
Typical Sections
Figure
D Proposed
Plan Sheets
Figure
E Option 1 Plan & Profile
Figure
F Option 2 Plan & Profile
Figure
F-1 Option 2
Cross Sections
Figure
G Option
3 Plan & Profile
Figure
G-1 Option 3 Cross
Sections
Figure
H Option
4 Plan & Profile
Figure
J Construction Sequencing Plan
APPENDICES
Pavement Design Memorandum
Geotechnical Report
Public Information Meeting
Utilities Contact
Information
Project Pictures
EXECUTIVE SUMMARY
Bartlett
& West Engineers was selected in May 2004 by the City of Lawrence to provide surveying and engineering
services for the design of Kasold Drive from 15th Street to Clinton Parkway. As a part of these
services, a preliminary study report was completed to review several options
for completing the project. This report highlights four of the many options
that were considered.
Kasold Drive is an arterial street in west Lawrence that carries approximately
20,000 vehicles per day. The future traffic projections indicate that
there will be 31,000 vehicles per day in 2025. The existing roadway is
generally a four lane divided section, which includes a grass median. The
right-of-way along the route is minimal in most areas for an arterial
classification. In addition, sidewalks do no exist on either side of the
road for most of the route. The route is surrounded by mostly residential
properties, except for the commercial areas that exist at both ends of the
project near 15th Street and Clinton Parkway.
This
stretch of Kasold Drive is characterized by several
hilly areas where the vertical curves along the road are short and
choppy. The vertical curves are substandard to todays engineering
criteria, and they create sight distance hazards in most locations along the
route. In addition, an 11.2% street profile exists along Kasold Drive just north of Augusta Drive, which exceeds generally
accepted criteria for arterial streets. The existing pavement is
seriously deteriorating, and the City maintenance crews are constantly working to
patch pavement areas in most locations along this stretch of Kasold Drive. Furthermore, the openings
in the grass median to provide left turn movements do not provide refuge areas
wide enough to protect vehicles trying to turn and get out of the way of
through traffic. It is also common to see traffic stacking up beyond the
provided turn lanes at the signalized intersections, especially for southbound
vehicles turning from Kasold Drive onto eastbound Clinton Parkway. The bottom line is that
there are a lot of obstacles along this roadway that create frequent
opportunities for accidents, and this condition will only get worse as the
traffic volumes continue to grow.
This
stretch of Kasold Drive is surrounded by
utilities. Westar Energy has an overhead main transmission and
distribution line adjacent to the roadway from the south end to the north
end. Aquila, SBC, and Sunflower Broadband all
have facilities along the road, mostly on the west side to serve the Alvamar
Estates area. Finally, the City of Lawrence has an above ground water tank
at approximately 19th Street and Kasold Drive. In addition, the City has a 12 water main from 15th Street to Clinton Parkway, mostly under the existing
pavement and median. The City also has a 6 line in the median from the
water tower sight south to Augusta Drive. The relocation of the
utilities will be an important part to the overall success of this
project. The utilities will need to be coordinated early in the design
process to ensure that their facilities are appropriately relocated prior to
the commencement of the road construction.
The
preliminary design elements of this study have led to several
conclusions. First, vehicles turning left along Kasold should have a
dedicated left turn lane allowing the driver to move their vehicle out of the
flow of traffic. Therefore, the grass medians should be removed in favor
of left turn lanes for even the residential street locations.
Furthermore, the traffic analysis indicates that geometric improvements need to
be made at Kasolds intersections with 15th Street and Clinton Parkway. A right turn only lane
needs to be added for northbound traffic approaching 15th Street, and dual left turn lanes and a
right turn only lane are necessary for southbound traffic approaching Clinton Parkway. Second, one of the
biggest issues with Kasold Drive today is the condition of the
pavement. The City of Lawrence has changed its standard
pavement section dramatically since Kasold was originally constructed.
The existing pavement was placed on compacted soil. The proposed pavement
section will consist of either 12 of asphaltic or 10 of concrete pavement,
both laid on a 4 drainable base, which is placed on 9 of treated
subgrade. To further protect the section from deterioration due to
moisture, edge drains will be used along each edge of the pavement. If
the asphaltic pavement option is selected, then Bartlett & West recommends
using concrete pavement between 15th Street and Seminole Drive and between Augusta Drive and Clinton Parkway to protect the project from
pavement issues that are common around Lawrence at intersection locations with
significant stopping and starting and turning movements. Finally,
pedestrian access is a key element of this project. The City of Lawrence prides itself on its facilities for
pedestrians and cyclists. However, this section of Kasold presently does
not have a sidewalk on either side along most of the route. All but one
of the options presented in this study provide for a 10 wide recreation path
along the west side of the new roadway. This recreation path will connect
the recreation paths along Clinton Parkway and Kasold Drive south of Clinton Parkway to the sidewalks along 15th Street and Kasold Drive north of 15th Street. These connections will
help the City of Lawrence to continue to upgrade the
access it provides its citizens and visitors.
Four
options are presented in this study. The first option is to remove and
replace the existing pavement, which will minimize the overall construction
costs while still improving the driving surface. The disadvantages
heavily outweigh the benefits to this option. The second, third, and
fourth options are all based on a new street profile that will improve the road
for the traveling public and pedestrians. The second option is a complete
road reconstruction with a new recreation path on the west side. The
grades are largely improved and the benefits of this option certainly outweigh
the disadvantages. The third option is almost identical to the second
option except for that the street profile north of Augusta Drive is slightly flatter.
Generally, a flatter slope would be attractive, however this leads to many
problems in this area of the project. Significantly more retaining wall
will be required due to the flatter profile. These additional retaining
walls will have a negative affect on sight distances for residents trying to
get out of their homes on the east side of Kasold Drive. The benefits
still outweigh the negatives on this third option. Finally, the fourth
option considers using the second options profile, but reducing the project
limits to 15th Street to West 22nd Street. Like the first option,
this is being considered to reduce construction costs. This option has
all the benefits of the second option, except that the intersection and street
grade improvements near the Clinton Parkway intersection are not
completed. These intersection improvements are critical to the overall
success of the project. Therefore, the fourth option is less desirable
than the second or third option.
A key
element to this study is the construction sequencing and schedule. It is
desirable to have the project complete by the end of 2005 and our sequencing
plan is based on this premise. The proposed sequencing plan will close Kasold Drive for a 10-14 week timeframe to
reconstruct the north leg of the intersection of Kasold Drive and Clinton Parkway and the south leg of the
intersection of Kasold Drive and 15th Street. After these intersections
are reconstructed, the remaining portion of the project will be constructed one
half at a time. This will allow traffic to be carried through
construction for the majority of the project. The schedule of the project
will be largely impacted by the relocation of utilities. The utility
companies will have to be a part of the planning process from the very
beginning of the final design phase. The more time they have to react and
relocate the better the likelihood is that the project will be complete by the
end of 2005. Overall, the completion date is a very aggressive timeframe,
but can be accomplished if the utilities are allowed to get started soon and
the weather cooperates throughout the year. Any delay in the relocation
of the utilities may result in the inability to complete the project in 2005.
Finally,
the recommendation portion of the study provides a couple tools to manage all
the pieces of this complex project. There are several individual
questions that have been asked along the way, including which pavement type to
use, the number of lanes necessary, etc. The matrix provided in the
recommendation section assists with trying to consider all factors of the
project and weighting them to provide an overall score. The
recommendation section concludes with the recommendation to proceed with the
second option presented in the study. While the second option is not the
cheapest option, it is also not the most expensive. In addition, the
second option provides the most common sense approach to balancing all the
wants and needs of the project into a manageable and sensible solution.
EXISTING CONDITIONS
Kasold Drive between 15th Street and Clinton Parkway is a four lane arterial roadway
that presently carries about 20,000 vehicles per day. Traffic projections
indicate that there will be 30,000 vehicles per day in the year 2025.
This portion of Kasold Drive was constructed in the early
1970s.
The
existing roadway can be characterized as a four lane road section with a
divided grass median throughout most of the project. There are median
openings at all of the side roads to allow for access into local residential
and commercial areas. Left turn only lanes are provided only at the
signalized intersections, but not at any of the unsignalized intersections, other
than West 22nd Street.
This
section of Kasold Drive is surrounded by three types of
land uses. First, there are residential properties along both sides of
the route. More specifically, residential uses are prevalent between West
22nd Street and Seminole Drive on the west side and between West 22nd
Terrace and just north of Scioto Drive on the east side. For the most
part, this is mostly single family housing, other than a few duplex units on
the west side near Seminole Drive and the Quail Creek Apartment complex between
Augusta and West 22nd Street on the west side. Second,
commercial areas exist at each end of the project. At Clinton Parkway, the Hy-Vee Shopping Center exists at the northwest corner
of Clinton Parkway and Kasold Drive. The Hy-Vee shopping
extends from Clinton Parkway to West 22nd Street. The shopping center
includes the grocery store, a bank, a restaurant, and an associated strip
center with a variety of retail stores. At the southwest corner of 15th Street and Kasold Drive, there are offices in place,
included a Coldwell Banker Real Estate Office and another office building.
Finally, the third entity is the ground owned by the KU Endowment
Association. Presently, this is undeveloped ground that is located on the
east side of Kasold Drive between 15th Street to a point just north of Scioto Drive.
This
stretch of roadway is one mile in length and there are six side roads and
twelve individual properties that have direct access to Kasold. The
following table shows the details for each of the side roads that intersect
Kasold throughout the project length.

Existing
Right-of-Way/Easements
The
original Kasold Drive road record was dedicated in
1904. Since that time, additional right-of-way has been acquired at
different times throughout the life of Kasold Drive. Presently, the existing
right-of-way varies throughout the project limits.
Beginning at the south end of the
project, the right-of-way varies drastically between Clinton Parkway and West 22nd Street. At Clinton Parkway, the right-of-way is approximately
192.5 in width. The right-of-way varies to a point just north of West 22nd Street, where the right-of-way becomes
50 each side of the section line, which is coincidental with the centerline of
the roadway.
The
right-of-way line on the west side remains at 50 from the section line
(centerline) from West 22nd Street to Scioto Drive. On the east side of
Kasold Drive, the right-of-way line is 50 in width between West 22nd
Street and a point approximately 300 north of West 22nd Street, at
which point the right-of-way line becomes 35 on the east side. The
right-of-way line on the east side remains 35 to a point about 100 south of Scioto Drive, except for one location.
The right-of-way in front of the Kincaid Addition is actually 60 from the section
line (centerline) due to a more recent plat.
The
right-of-way on the east side remains at 50 from a point about 100 south of
Scioto Drive to the intersection of 15th Street & Kasold Drive,
except in one area. The right-of-way on the east side of the Stoneland Court Subdivision, just north of
the City water tower, is 35. On
the west side of Kasold Drive, the right-of-way line is 90
feet from the section line (centerline) from Scioto Drive to Seminole Drive. The extra right-of-way
width to the west is there to accommodate the frontage road that exists along Kasold Drive from Scioto Drive to Seminole Drive.
As
mentioned in the previous paragraph, the right-of-way on the east side remains
at 50 from Seminole Drive to the intersection of 15th Street &
Kasold Drive. In addition, the same 50 wide right-of-way exists on the
west side of Kasold from Seminole Drive to 15th Street.
Utility easements exist along
certain portions of the route, many of which are aligned in an east-west
orientation, so they intersect the existing right-of-way at one location.
There are a few easements that parallel the existing right-of-way. First,
a 15 utility/pedestrian easement exists on the west side of the Kasold Drive right-of-way between West 22nd Street and Augusta Drive. Second, a 7.5 utility
easement parallels the west edge of the Kasold Drive right-of-way between Augusta Drive and Scioto Drive.
Further
detail showing the existing right-of-way and easements is shown on Figure A,
which shows the existing plan view of the project.
Geotechnical Investigation
GeoSystems/Kleinfelder,
Inc. was hired to drill borings at 14 different locations along the existing
route. The borings were drilled to a maximum of 11 in depth or auger
refusal, whichever occurred first. Auger refusal generally indicates that
unweathered rock is present.
Generally
speaking, the project can be broken into two parts when considering the
findings of the borings. First, the north half of the project, north of
Scioto Drive, contained rock at elevations approximately 5.5 to 6 deep in all
locations. The materials found were pavement on top of red-brown fat
clays, which all lies on top of limestone rock formations. The limestone
prevented the borings from reaching the maximum depth of 11. Second, all
borings taken on the portion of the project south of Scioto Drive were taken to the 11 maximum
depth. Much of the material found along the south half of the project
included highly weathered shale that is characterized as soft to moderately
hard. GeoSystems indicated that this material should be able to be
excavated using traditional excavation techniques without the need for
hammering or blasting. In addition, some areas of the south portion of
the project were described as fat clays.
Somewhat
surprisingly, no ground water was found in any of the borings during a time of
2004 that was pretty wet. The City of Lawrence and adjacent residents both have
witnessed ground water in this area. Some residents have even indicated
that springs exist in the area of the project. While no ground water was
found at the boring locations, the project pavement section will provide a
subsurface drainage system to handle seasonal ground water.
The 14
borings are shown on the plan and profile sheets. In addition, a full
copy of the geotechnical report can be found in the appendices.
Utilities
Power, telephone, cable
television, gas, and water lines exist along much of Kasold Drive between 15th Street and Clinton Parkway. The one main utility that
is not located next to this stretch of the roadway is sanitary sewer.
Bartlett & West Engineers located the utilities as marked by Kansas One Call and the City of Lawrence Department of
Utilities locator services and this information is provided on the plan and
profile sheets presented in this report.
Each
utility company was sent a set of drawings that showed the existing surveyed location
for their surface and underground infrastructure. Bartlett & West
asked each utility to review the drawings and provide feedback concerning their
present locations. A list of utility contacts is included in the
appendices. Pertinent information regarding each individual utility is
discussed in more detail below.
Westar
Energy
Westar
Energy is prominent along Kasold Drive. There are main
transmission and distribution lines located on overhead power poles and
distribution lines located underground along parts of the route. Westar
also provides street lighting on overhead power lines located in the grass
median throughout much of the route.
The
power poles and overhead power lines that carry transmission and distribution
lines exist along the east side of the project from Clinton Parkway to a point just north of Tam OShanter Drive. The poles and lines then
cross over the roadway and remain on the west side of Kasold Drive from north of Tam OShanter Drive to 15th Street. This facility is of utmost
concern due to the costs involved to relocate the poles and lines.
Bartlett
& West, Westar Energy, and the City of Lawrence have met regarding the existing
power facilities. The intent of the proposed project is to allow the
overhead power lines to remain as they exist for as much of the route as
possible. Westar has agreed that they will provide clearances from the
existing ground line to the sag points of the overhead lines for any areas of
concern once the final profile is accepted. There will most likely be
between two and four poles that will have to be relocated to accommodate the
new road section.
The
overhead transmission and distribution lines were in place prior to the road right-of-way
being expanded. Therefore, any costs required to rise, lower, or relocate
those facilities will have to be borne by the City of Lawrence as a part of this project.
Aquila
Inc.
Aquila has a 4 gas main that exists
along the entire route. The gas line is a steel line that is well east of
the project limits from Clinton Parkway to West 22nd
Terrace. Just north of west 22nd Terrace, the gas line heads
to the east for 60 +/- and then turns north under the existing Kasold
Drive. The section of gas line between West 22nd Street and Augusta Drive was relocated a few years ago
due to a local development project. This portion of the gas line is PVC. Around Augusta Drive, the gas line becomes steel
again. On the west side of Kasold Drive, the gas line north of Augusta Drive to 15th Street is then located west of the
existing curb and gutter for the remainder of the project.
Bartlett
& West visited with Chuck Hoag of Aquila about the potential relocation of their
facility. Aquila indicated that they need 60 to 90 days to relocate the
facility. Bartlett & West will need to submit the final profile to
them before their engineer can begin design of the new facility.
Sunflower
Broadband
Sunflower
Broadband provides cable television, internet, and telephone service to
customers along this route. Bartlett & West has discussed this
project with Jim Day of Sunflower Broadband. Jim indicated that
Sunflowers facilities are aging in this area, and much of the existing coaxial
cable is buried without a conduit. Therefore, they are welcoming the
opportunity to replace their aging infrastructure with conduit encased cable
lines.
Sunflower has fiber optic lines
in two locations along the project. First, a fiber optic cable exists
along the south side of 15th Street and crosses Kasold Drive. Due to 15th Street being the tie-in location for
the north end of the project, it is considered unlikely that this line would be
negatively impacted. Second, a fiber optic line exists on the east side
of Kasold Drive between West 22nd Terrace and a point about 150
north of West 22nd Street. While it does not appear likely
that this line would need to be relocated, it is too early to determine for
sure if that is the case. Jim indicated that if either of these fiber
optic lines needed to be relocated then additional time would be necessary for
their relocation.
Jim
indicated that the main issue is actual location of their new fiber
lines. Sunflower would entertain the notion of being located in the same
trench as telephone and power. However, they do not want to be near the
gas company. In addition, Jim expressed concern about where they might
need to relocate. Significant grade changes create challenges with
providing a new facility while keeping the existing service available.
Interruption of service is not an option.
Jim felt
that it would take 60 to 90 days to complete the relocation of their
facility. This time frame is dependent on two main items. First,
the weather would add delays to the relocation. In addition, if rock
excavation is encountered then they would experience delays.
Finally,
Sunflower Broadband will be responsible for all relocation costs associated
with this project.
SBC
SBC has facilities along much of the
route, including a fiber optic cable that runs down the middle of the existing
median. Most of their facilities are buried cables along the west side of
Kasold
Drive. SBC has indicated that the fiber optic line that
exists in the median could be taken out of service and rerouted temporarily
during relocation of the existing line.
Bartlett
& West met with Janice Bowers and Fred Laubach to discuss their
facility. Janice and Fred verified the location of their utilities as
shown on the drawings sent to them. In addition, SBC noted a few minor areas that
needed to be updated, which have since been completed by Bartlett & West.
SBC indicated that they will need 6
months from the time that they receive final plans to relocate their facility.
SBC will be responsible for all
relocation costs associated with this project.
City of Lawrence Water
There
are two City of Lawrence waterlines that exist along Kasold Drive between Clinton Parkway and 15th Street. Both lines are
approaching 40 years old.
First,
there is a 12 low pressure line that extends from the north end of the project
to the south end of the project. This line is located under the
northbound lanes from 15th Street to Tam OShanter. The 12
line jogs to the west at Tam OShanter and is located in the existing median
from Tam OShanter to West 22nd. At West 22nd, the
roadway enters two reverse curves, which moves the centerline of the road to
the west.
The 12 waterline continues
directly south, which results in the waterline crossing under the northbound
lanes. Just southeast of the intersection of Kasold Drive and West 22nd
Terrace, the waterline is located east of the existing curb line.
Second, a
6 high pressure line exists in the median from the water tower site, which is
between Scioto Drive and Tam OShanter Drive, to Augusta Drive. The 6 waterline turns to
the west at Augusta Drive to provide service for the
existing residential area west of Kasold Drive.
The City of Lawrence Department of
Utilities has indicated that they would prefer to relocate both of these lines
outside of the new pavement limits. The early indications are that both
lines would be located on the east side of the proposed Kasold Drive section. There will be
limited locations where the waterline will need to remain under pavement for
very short stretches. Both water lines provide services to adjacent
houses. Therefore, the Utilities Department will determine how future
water service will be provided to these homes.
Each
utility agreed that it would be helpful to get all interested parties at a
meeting soon after the final profile is adopted so that discussions can begin
regarding relocation. Bartlett & West would propose holding this
meeting as one of the first items to be taken care of in the final design
phase. Relocating the utilities needs to be completed prior to the
bidding of the project. There is some time available in Phase 1 of the
construction project to allow for final work associated with the utility
relocations.
PRELIMINARY DESIGN
Bartlett
& West provided a traffic analysis for the existing and future traffic
projects. In addition, to the traffic volume analysis, Bartlett &
West reviewed accident data relating to this stretch of Kasold Drive. Based on the traffic
analysis, a proposed lane configuration layout was developed. Finally,
the traffic signals were analyzed to determine present and future needs.
Perhaps
the most critical result of the traffic analysis is the recommendation to close
the access to Kasold Drive at Scioto Drive. This analysis is
discussed with the Traffic Analysis portion of the report below.
Traffic Analysis
The
existing four lane section on Kasold has two through lanes in each direction,
separated by a grass median. The intersections of Kasold with: West 22nd Street, Augusta Drive, Scioto Drive, Tam OShanter Drive, and Seminole Drive are all stop-controlled
intersections. Currently there are median breaks on Kasold at each
intersection. These median breaks do not provide any left turn storage
for vehicles turning off Kasold. The absence of left turn storage increases
accident potential and also slows the through traffic on Kasold, thus reducing
capacity as well.
The City of Lawrence provided A.M. and P.M. peak hour
turning movement counts for each of the side street intersections. These counts
were used to evaluate the need for left-turn storage on Kasold. By
eliminating the existing median, there is an opportunity to provide an
additional turning lane at these intersections and not increase the width of
the roadway. There have been engineering studies by the Federal Highway
Administration, ITE and others on the use of left-turn lanes at unsignalized
intersections. All studies come to the same conclusion; the addition of
the left-turn reduces accidents 30% to 60%. In looking at each of the
side street locations, it is necessary to provide left-turn storage on Kasold.
When
considering the existing geometrics of each side road, the intersection of Scioto Drive and Kasold immediately raises
safety concerns. Scioto Drive currently intersects Kasold at
about a 17% grade. There is also a connecting frontage road very close to
the intersection with Kasold. The existing traffic counts show that there
are a total of four vehicles exiting Scioto Dr. in the morning and evening peak
hours. Augusta Dr. to the south and Tam OShanter
to the north still provide close access points to the neighborhood, so the
closing of Scioto Drive would not provide any major
negative influence on the local traffic using the roadway. Fire
protection and emergency access would still have adequate routes to the
neighborhood. In addition, both the Fire and Police Departments raised no
concerns about the potential closing of Scioto Drive. The combination of low
traffic volumes, poor geometrics, proximity to the adjacent frontage road, and
adequate access by other routes, led us to the recommendation of closing the
direct access between Scioto Drive and Kasold Drive.
If the
direct access from Scioto Drive to Kasold is eliminated, there
would be an opportunity to narrow the roadway section to four lanes between Augusta Dr. and Tam OShanter. This
roadway section would be narrower than existing and provide an opportunity to
minimize impacts to adjacent landowners, while trying to provide the recreation
path adjacent to the proposed roadway. In narrowing the roadway to a four
lane section, left-turn access would not be allowed through the southbound
lanes on Kasold to the homes on the east side of the road. This access will
be blocked by constructing a narrow center island to eliminate left turns in an
area where no center turn lane will be available. Currently, these homes do not have
left turn access due to the existing grass median. This would force a
southbound vehicle to go further south, make a U-turn at the signalized
intersection of West 22nd Terrace & Kasold Drive and then back
north to their residence.
Right
turn lanes for southbound traffic on Kasold at W 22nd Street and W 22nd Terrace
have been added to help maintain through traffic movement on Kasold.
These lanes will be replaced as a part of the project.
Traffic
Signal Analysis
Bartlett
& West received both A.M. and P.M. existing peak hour turning movement
counts from the City for the three signalized intersections along this
project (Clinton Parkway, West 22nd Terrace, and 15th Street). Existing AADT (19,780
vehicles per day) and year 2025 AADT (31,000 vehicles per day) were provided be
the City of Lawrence. A growth factor using the
existing and future traffic volumes was determined to be 2.1%. This
factor was then used to adjust all of the turning movements at the three
intersections to the year 2025. This includes increasing traffic volumes
on Clinton Parkway and 15th Street at the same growth factor.
The existing and future year turning movement volumes are shown below.

Trafficware
Synchro 5, Traffic Signal Coordination Software was used to analyze the signalized
intersections at Clinton Parkway & Kasold Drive, West 22nd
Terrace & Kasold Drive, and 15th Street & Kasold Drive.
Synchro 5 computes the capacity and Level of Service for signalized
intersections in accordance with the procedures of the 2000 Highway Capacity Manual, Chapter 16. Synchro provides
intersection capacity analysis and timing optimization. Synchro
incorporates the SimTraffic traffic simulation model to provide traffic
performance Measures of Effectiveness (MoE) beyond those provided by the HCM. These include average
and maximum queue lengths, which are useful to evaluate turn lane storage
requirements.
A
current Level of Service was determined for each of the signalized
intersections after evaluating the current intersection geometrics and traffic
volumes. Year 2025 traffic projections were then inserted into the model
to obtain a Level of Service of each of the intersections while maintaining the
current roadway geometrics.
The two
main intersections at Clinton Parkway & Kasold and 15th Street & Kasold both currently
operate in the PM peak hour at a Level of Service (LOS) C. In looking at the future
year 2025 scenario, both intersections will have significant delay due to the
increased traffic volume. It was our assumption that this study will look
at improvements to the north leg of Kasold at Clinton and the south leg of
Kasold at 15th Street to help reduce the overall delay. The
improvements identified will be a part of, and planned to work with, several
improvements necessary to improve the operation of the intersections in the
future.
There
were several different intersection improvements that were considered along Kasold Drive.
- At 15th Street, it is necessary to add a
northbound right turn lane on Kasold, as well as lengthening the existing
northbound left turn bay. In order to fully separate northbound
right turn vehicles, a 500 storage length is required, or maximize the
storage available prior to the Seminole Drive intersection.
- At the intersection of Kasold Drive and Clinton Parkway, a southbound right turn
lane was added. Dual left turn lanes were also added.
The
results of the analysis of the existing, future and future with improvements
are shown below. Additional Synchro model output and summaries are
available upon request.

Accident
Analysis
Accident
history was provided by the City for the years 2001-2003. Intersection Collision Diagrams were developed
for each intersection and can be provided upon request.
The un-signalized
T-intersections between 15th Street and Clinton Parkway showed an accident pattern due
to the lack of left turn lanes from Kasold Drive to the side streets.
Bartlett & West is proposing to provide the left turn lanes at all side
roads. This should greatly reduce that accident pattern.
The
intersection at 15th Street and Kasold Drive had a total of 38 accidents in
the three year period. Twenty-six of the 38 accidents were left turning vehicles
colliding with opposing through vehicles. The intersection currently has
protected/permissive left turns in all four directions. The
northbound/southbound left turning movements meet KDOTs warrants for protected
left turn phasing. The intersection also meets the criteria for four or
more accidents in one year, six or more in two years occurring on one
approach. In addition, the intersection also meets the criteria for six
or more accidents in one year and ten or more in two years occurring on both
approaches. The collision diagram for the intersection can be provided
upon request. Eliminating the permissive left turn movements from the
intersection should reduce the number of accidents, but might cause increased
overall delay at the intersection.
The
intersection at Clinton Parkway and Kasold Drive had a total of 42 accidents in
the three year period. Fourteen of these accidents were vehicles turning
left off Kasold Drive to Clinton Parkway colliding with opposing
vehicles. Currently this movement is protected/permissive from Kasold Drive. The installation of dual
left turn lanes on the north leg of Kasold will require the north/south turning
movements to be protected only. East/west left turns off Clinton Parkway are already protected. This
phasing change will reduce the number of accidents at the
intersection.
Although
the improvements to Kasold at 15th Street & Clinton Parkway dont solve the overall
operation problems of the intersections, they should be a part of the overall
solution. The overall solution will need to include intersection
improvements at the other legs of the intersection before the intersection will
be considered to operate at an efficient level.
Traffic
Analysis Recommendations
This
project will take significant steps to increase safety along the Kasold
corridor. Below is a summary of the recommendations based upon the
traffic analysis, accident analysis, and signal analysis.
- Close direct access from Scioto Dr. to Kasold.
- Provide left turn storage on
Kasold to all side roads
- Provide a four lane section
with a narrow median from Augusta to Tam OShanter
- Replace southbound right
turn lanes at W 22nd Street & W 22nd
Terrace.
- Provide a right turn lane
and dual left turn lanes for southbound traffic on Kasold at Clinton Parkway
- Provide a right turn lane
for northbound traffic on Kasold at 15th Street. Left turning phasing
for northbound/southbound left turn movements on Kasold Drive at 15th Street should be changed to
protect only and the signals modified accordingly.
Finally,
Figure B graphically shows the recommendations for the number of lanes at all
locations along Kasold Drive between 15th Street and Clinton Parkway. Specific transitions and
lane limits will be determined during the final design phase of the project.
Pavement Design
As a
part of the study Bartlett & West was responsible for examining rigid and
flexible pavement systems. The purpose of examining the two pavement
systems is for the design and comparison of pavement systems for the
project. The pavement systems are designed for the street in accordance
with the methods described in the American Association of State Highway and
Transportation Officials Guide for Design of Pavement Structures, 1993 edition
(AASHTO Guide). Several issues are involved in the pavement analysis,
most of which are summarized in the following discussion. The pavement
analysis report can be found in its entirety in the Appendices.
Design
Parameters
The AASHTO
Guide pavement design method requires input parameters relative to the pavement
system which describe the traffic loadings that will be imposed on the system,
soil conditions, concrete parameters, pavement design reliability, and pavement
serviceability. The pavement design criteria were taken from the Kansas
Department of Transportation and AASHTO. The analysis period for
the pavement design is 30 years. Listed below are the values used for
these design parameters in this report.
Traffic
Traffic
loadings over the design life of the pavement are expressed as equivalent
18-kip single axle loads (ESAL). This expression is used as a
common unit of measure which allows summation of different axle loads and
configurations from a mixed traffic stream. This means that cars and
trucks can be accounted for based on axles and then summed together.
2025
future traffic volumes, provided by the City of Lawrence, were used in the
analysis. These traffic volumes and distribution are shown in the
pavement analysis report in the Appendices. Assuming a linear
relationship, the traffic volumes are averaged to calculate the daily two-way
traffic volume for the 30 year analysis period. A directional
distribution factor of 60% and a lane distribution factor of 100% are applied
to the daily traffic volume.
Once the
traffic volume is established, the traffic mix must be determined to assess the
weights and axle loadings which will be applied to the pavement system over the
analysis period. Due to the lack of statistical information in the
immediate area of the proposed improvements, average distribution values were
used. These values are based upon similar traffic mixes, as stated in the
Kansas Department of Transportation (KDOT) study Kansas Truck Weight Survey 1994 and
1992-1994 Combined. Refer to the report in the Appendix for a
complete listing of the traffic distribution. Average axle load
equivalency factors that are also taken from the study to convert the loadings
into ESALS.
Soil Conditions
Site
geotechnical investigations were performed by GeoSystems/Kleinfelder in June
2004. Soil samples were taken from 14 borings extending six to ten feet
below the existing ground surface drilled on the proposed project site.
The
borings were monitored while drilling and after completion for the presence and
level of groundwater. Groundwater was not observed in the borings.
This may have been influenced by the time of year and the low permeability of
the cohesive soils encountered in the borings.
Typically, the subgrade material
is a fat clay material. Most of the soils encountered in the borings will
have a high shrink-swell potential. Based on this typical classification,
we estimate the soil design characteristics to be:
Subgrade Modulus,
k,
= 165 p.c.i.
Modulus of
Elasticity
= 4000 p.s.i.
The
subgrade modulus was adjusted to account for loss of support using AASHTO Guide
methods. A loss of support factor of 0.80 was used for a fly-ash treated
subgrade. The resulting effective modulus of subgrade reaction is 100
p.c.i.
Fly-ash
treatment of the clay subgrade soils will significantly reduce the shrink-swell
potential. The City has had success on recent projects using fly-ash
treated subgrades. Therefore, only fly-ash treated subgrades were looked
at in this report.
Other
Design Parameters
The
characteristics and joint transfer information pertaining to the rigid pavement
system and statistical standard deviation estimates were generally obtained
from recommendations listed in the AASHTO Guide. A reliability factor of
90%, design period of 30 years, and serviceability loss of 2.5 also reflect
values recommended by AASHTO Guide for urban arterials.
Pavement
Systems
As a
part of the pavement design, both rigid and flexible pavement systems were
analyzed. The flexible system is a 2 asphaltic concrete surface course,
10 asphaltic concrete base course, a 4 bound drainable base course on a 9
fly-ash treated subgrade. All told, the flexible pavement system will be
25 thick. The rigid system analyzed includes a full-depth 10 concrete
pavement with a 4 bound drainable base on a 9 fly-ash treated subgrade.
Therefore, the rigid pavement system will be 23 thick.
In
addition to the pavement section, edge drains will be used on both sides of the
roadway to accommodate the proper drainage of subsurface ground water away from
the pavement section.
Regardless
of the pavement system used, the pavement will be considerably thicker than the
existing pavement system, which generally is a concrete base with an asphaltic
overlay. The real difference is that the base of the older roadways was
not treated with bound drainable bases or fly ash.
Economic
Analysis
The
KDOTs Life Cycle Cost Analysis Procedure was chosen to make the economic comparison of
the two alternatives. Typical maintenance activities for both flexible
and rigid systems were used to determine future maintenance costs. These
future maintenance activities for flexible systems include a two inch mill and
overlay every 10 years after construction. Crack filling will occur
throughout the life of the pavement. Rigid systems do not have a future
maintenance planned, because they are assumed to last for the entire 30 year
design life. Crack and joint sealing will occur as necessary.
This analysis procedure assumes that for major rehabilitation projects, the
salvage value at the end of the analysis period will be equivalent. Thus
this value does not enter into the present worth analysis.
Quantities
were calculated for the two pavement systems and future overlays using
guidelines from KDOTs Design Manual Volume II. Using these
quantities and recent bid tab information from KDOT, initial construction costs
were determined for each of the pavement systems.
In the
life cycle cost analysis, the present cost of future actions are inflated by
5%. All future costs and salvage values are then discounted at a rate of
7% to attain a present worth to be used for comparison. The present worth
calculations for each pavement system are shown below. The following is a
summary of the present worth costs of the both pavement system alternatives:
Flexible Alternate
$1,574,248.58
Rigid Alternate
$1,815,405.74
Flexible
Alternate, which is a 2 surface course, and a 10 base course on a 4 bound drainable
base on 9 of fly ash subgrade, proved to be the most economical section.
Typical Sections
The
typical section for the roadways is impacted by several issues. Available
right-of-way, traffic capacities, and existing grades are all issues that
drastically affect a proposed typical section. In addition, the type of
pavement will affect the typical section. Bartlett & West worked with
City staff to develop typical
sections that work for the Kasold Drive project.
Before
proceeding to the typical sections, a few main issues need to be briefly
recapped to determine how they impacted the typical sections. First, the City staff indicated that their
preference was to use a typical section that would fit within the existing
right-of-way, which will ultimately reduce project costs. Second, the
traffic analysis provided in the previous section determined the number of
lanes needed throughout the project. This analysis dictates the geometric
configurations at the signalized intersections. It was decided that a
comparison between asphaltic and concrete pavement would be included in this
study. The typical sections shown in the study do not reflect asphaltic
or concrete pavement material. Details on pavement type will be addressed
during final design. However, the intent of the typical sections is valid
no matter which pavement system is selected.
Typically,
the City typical section for an
arterial roadway would have 12 driving lanes, a 2 wide curb and gutter
section, 6 between the curb and gutter and the edge of the sidewalk/recreation
path, and a 6 sidewalk or 10 recreation path. Assuming that a typical
arterial roadway would have four through lanes and one center turn lane, and
then the typical section would consume 88 if there are 6 sidewalks on both
sides. This does not take into account tie-in grades or recreation
paths. Typically, 100 of right-of-way is needed for an arterial road
section. However, there is a fairly significant stretch of the Kasold Drive project that provides only 85
of right-of-way. Therefore, the normal City of Lawrence typical section will need to be
revised throughout this area as a minimum.
The
typical sections discussion that follows will progress from Clinton Parkway to 15th Street. Again, there are some
details for these typical sections throughout the project that will have to be
addressed as part of final design. However, the general intent of the
typical sections for each area of the project will be followed during the design
phase. These typical sections are for the preferred road reconstruction
option. Typical sections for removing and replacing the pavement as it
exists today, shown on Figure C, have been included but no discussion is
included.
General
Typical Section Discussion For Preferred Road Reconstruction Options
The
typical section defined itself for the most part after reviewing several
alternatives for typical sections throughout the project. Generally
speaking, the typical sections will have 12 lanes, 2 curb and gutters, and a
10 recreation path on the west side of the proposed roadway. There will
be two through lanes in each direction for the entire length of the
project. Left turn only and right turn only lanes will be added as
necessary throughout the project. The driving lanes will have a 3/8 per
ft. cross slope. The recreation path location will be 2 from the back of
curb for the majority of the project. Retaining walls will be required,
mostly on the west side due to the recreation path construction. Where
applicable, a 4 raised concrete median will be used to control traffic
movements.
The
grass median that exists on much of the project will no longer be a part of the
proposed typical section. This circumstance is due to the fact that the
number of lanes is increasing in many areas of the project without acquiring
additional right-of-way. In addition, center left turn lanes are
recommended for any turning movements throughout the project due to the traffic
volumes for Kasold Drive. The center left turn
lanes provide a measure of safety that will eliminate many of the rear end
accidents that occur on this stretch of roadway. The existing street
lights in the median will be moved to each side of the street.
Utilities
will be required to move to accommodate the new typical section. These
utilities may locate under the recreation path for much of the project in
separate conduits. The typical section has been designed to try and
minimize the disturbance to the existing overhead power facilities.
From Clinton Parkway North to 150 South of West 22nd
Terrace
The
typical section at Clinton Parkway will be the widest section
required for the project. This typical section is shown on Figure C and is labeled as the Kasold Drive and Clinton Parkway Intersection
Typical Section. At the intersection there will be two through lanes for
both northbound and southbound traffic. In addition to the through lanes
for the southbound traffic, there will be dual left turn lanes and a right turn
only lane. Therefore, the pavement section will be seven lanes
wide. The dual southbound left turn lanes will be separated from the
northbound through lanes by a 4 wide raised concrete median. The section
will include a 10 recreation path on the west side of the roadway. The
recreation path location will be 2 from the back of curb to the edge of the
recreation path. This area will require additional right-of-way or a
pedestrian easement so the recreation path can be constructed. A retaining
wall will be constructed along the east side to address the steep slope up to
the DCCCA.
The
critical issue at this intersection is that the existing condition is in a
failing state when considering the traffic capacity of the intersection.
It is very common that southbound traffic wanting to turn left onto eastbound Clinton Parkway will back up out of the left
turn lane and into one of the through traffic lanes. This is a safety
issue that will progressively worsen as traffic counts increase. The
seven lane section will alleviate the traffic capacity issues that exist at
this intersection today and it will maximize the effectiveness of the north leg
of the Kasold Drive and Clinton Parkway intersection in future
years. All legs of this intersection will need to be improved in the near
term to alleviate traffic capacity issues. The north leg will be
reconstructed as a portion of this project so that it works efficiently with
future improvements of the other legs of the intersection.
South
Side of West 22nd Terrace
The
south side of the West 22nd Terrace and Kasold Drive intersection will be very
similar to the existing condition. This typical section is shown on
Figure C and is labeled as the Kasold Drive and West 22nd Terrace
Intersection (South) Typical Section. This section requires five
lanes. There will be two southbound and two northbound through
lanes. The fifth lane will be for traffic traveling northbound wanting to
make a left into the Hy-Vee grocery store center. The northbound left
turn lane will be separated from the two southbound through lanes by a 4
raised median. The recreation path will continue on the west side.
However, its location will vary from 2 to over 10 from the back of curb to
the edge of the recreation path. This area may require some additional
right-of-way or a pedestrian easement to accommodate the construction of the
recreation path.
Between
West 22nd Terrace and West 22nd Street
In
addition to the two through lanes in each direction, there will be a center
turn lane and a southbound right turn only lane added to this section.
The grass median that exists in this stretch of the project will be replaced by
the center turn lane. The center turn lane maximizes the available storage
available between these two streets. The separation between the two
intersections is only about 250, which really minimizes the storage lengths
available. Therefore, maximizing those storage lengths will allow for
some stacking for residential traffic turning eastbound on West 22nd
Terrace and for residential/truck traffic turning westbound on West 22nd Street. The recreation path
location will vary from 2 to over 10 from the back of curb to the edge of the
recreation path. This area may require some additional right-of-way or a
pedestrian easement to accommodate the construction of the recreation
path. This typical section is shown on Figure C and is labeled as West 22nd
Terrace to West 22nd Street Typical Section.
Between
West 22nd Street and Augusta Drive
This
section of Kasold Drive will be very similar to the five
lane section that exists today. There will be two through lanes for both
the northbound and southbound traffic. In addition, there will be a right
turn only lane between West 22nd Street and Augusta Drive. Finally, the existing
grass median will be replaced with a center turn lane that will provide storage
and improve safety in this area. The existing sidewalk will be replaced
by the 10 recreation path on the west side of Kasold Drive. The recreation path
location will be from 2 behind the back of curb. This area will require
some additional right-of-way or a pedestrian easement to accommodate the
construction of the recreation path. This typical section is shown on
Figure C and is labeled as West 22nd Street to Augusta Drive Typical
Section.
Between
Augusta Drive and 400 South of Tam OShanter Drive
This
stretch of the project presents the most challenges relating to the typical
section. The right-of-way between Augusta Drive and Scioto Drive is only 85 wide. The west
side of Kasold Drive is a steep slope up from the
road to the backyards along Camelback Drive. The east side of the road
is bordered by homes that have direct access to Kasold Drive. The homes on the east
side are buffered by landscape berms and plantings. An additional
obstacle on the east side is the overhead power lines and associated poles,
which sit essentially at the right-of-way line. The design team
recognized the need to maintain the landscaping protection that exists for the
homes on the east side. Therefore, the typical section between Augusta Drive and Scioto Drive was built from the west
right-of-way line to the east. Minor temporary construction easements
will be necessary along this stretch of the project.
The
typical section will require retaining wall along most of the stretch between Augusta Drive and Scioto Drive on the west side, as well as
another area north of Scioto Drive. There are two typical
sections shown on Figure C. One of the typical sections is labeled as Augusta
Drive to Scioto Drive, while the other one is labeled as Scioto Drive to 400
South of Tam OShanter Drive. The distance between the retaining wall and
the back of curb on the west side will be 13, which allows for 1 between the
recreation path and the retaining wall, a 10 recreation path, and a 2 buffer
between the recreation path and the west back of curb. There will be two
through lanes in each direction. The through lanes will be divided by a
4 wide raised concrete median throughout the entire stretch of this typical
section. The purpose of the 4 raised concrete median is to prevent
southbound traffic from turning left into the homes on the east side of Kasold Drive. This is being done
because a center turn lane cannot be constructed through this stretch to
provide protection to turning vehicles. The sole reason the center turn
lane cannot be constructed is because of space limitations. Constructing a center turn lane
would necessitate the removal of the landscaping on the east side of Kasold,
which was deemed an unacceptable solution.
400
South of Tam OShanter to Seminole Drive
Generally
speaking, this portion of the roadway is bordered on the west by a frontage
road that provides residential access and on the east by the University of Kansas Endowment property, which is undeveloped
at the time of this study. Presently, there are no plans for development
of the KU property. Left turn lanes have been recommended for northbound
traffic turning onto Tam OShanter Drive and Seminole Drive. Westar Energys overhead
transmission and distribution lines have now crossed to the west side of Kasold Drive and become a controlling feature
throughout this portion of the project.
The
typical section labeled 400 South of Tam OShanter to Seminole Drive on Figure C indicates the road section to be
found along this stretch of the route. The 10 recreation path will be
built in the grass area between the frontage road and Kasold Drive. In addition, the recreation
path will be fit in between the existing power poles and proposed back of
curb. The pavement will be five lanes wide, which includes two through
lanes in each direction plus a center turn lane. This typical section
will require some temporary construction easement along the KU endowment
property.
Seminole Drive to 15th Street
The only
difference between the existing conditions and the proposed improvements for
the south leg of the intersection of 15th Street and Kasold Drive is the addition of a right turn
only lane. Therefore, the pavement section will be six lanes wide.
In addition to the right turn only lane, there will be two through lanes in
each direction and a left turn only lane for vehicles traveling northbound on Kasold Drive and turning westbound onto 15th Street. This typical section is
labeled as Seminole Drive to 15th Street and is shown on Figure C. Some temporary
construction easement may be needed along the KU Endowment property.
Traffic Signal Analysis
Bartlett
& West has analyzed how the Kasold Drive reconstruction will affect the
existing traffic signals at Clinton Parkway, 22nd Terrace and 15th Street.
Clinton Parkway & Kasold Drive
The City of Lawrence currently has a signal
replacement project underway. Our project will define the lane
configuration on the north leg of Kasold. Horizontal and vertical
alignments will also be established. The City will order poles and mast
arms that will work with our design.
Video
Detection is in place, so there will not be any in ground loops to replace.
22nd
Terrace & Kasold Drive
The
number of lanes will not change with our proposed design. However, the lane
configuration and geometrics will vary slightly from existing. The
existing poles and mast arms on three corners (NE, SE and SW) will have to be
moved to new bases to account for the vertical grade difference between the
existing ground and proposed design.
The
conduit that carries the traffic signal wiring will be in conflict with the
approximately 24 inches of pavement and subgrade preparation. That
conduit and cabling will have to be replaced from each of the relocated poles
to the controller.
Video
detection will be added to the existing signal system, which will eliminate the
need to cut detection loops into the new pavement section.
15th Street & Kasold Drive
Our
project will only affect the south leg of the intersection. All existing
poles and mast arms are outside the proposed curb alignment.
Currently the northbound and southbound left turning movements are
protected/permissive movements. There is a history of left turn accidents
caused by the permissive movement. These movements meet warrants for
protected left turn phasing. The intersection meets the criteria for four
or more accidents in one year, six or more in two years occurring on one
approach. The intersection also meets the criteria for six or more
accidents in one year and ten or more in two years occurring on both approaches.
The collision diagram for the intersection can be found in the
Appendices.
To
convert to protected only northbound and southbound left turning movements, new
poles and mast arms will have to be installed in the NE and SW corners of the
intersection. Left turn signals will be added.
Video
detection will be added to the existing signal system, which will eliminate the
need to cut detection loops into the new pavement section.
Storm Sewer Analysis
Providing
an adequate storm sewer system is vital to the success of designing any roadway
project. Road flooding is one of the biggest complaints heard from the
general public. Standard engineering practice is to intercept the 10 year
storm event and collect it through a system of inlets and pipes. Anything
larger than the 10 year storm will be carried overland on the roadway.
The proposed storm sewer system along Kasold Drive was designed according to these
standards. As usual the biggest concern when rehabilitating an existing
roadway is if the downstream storm sewer capacity.
The
drainage areas adjacent to this section of Kasold Drive are relatively small.
Storm sewer inlets have been placed according to width of spread
criteria. The width of spread refers to the distance that runoff carried
at the edge of a roadway extends from the curb. The width of spread is
determined by the cross slope of the roadway, the longitudinal grade of the
roadway, and the drainage area to the point of consideration.
The storm
sewer system was designed using concrete pipes, which is appropriate for an
arterial roadway. The storm sewer on the north half of the project
consists of pairs of inlets that connect across Kasold Drive and direct runoff to an existing
system west of Kasold Drive along the frontage road.
Therefore, there will not be a storm sewer main along this portion of the
project. The storm sewer on the south half of the project will parallel
most of Kasold Drive, with the storm sewer main
located along the west side of the road. The system will outlet into an
existing system along West 22nd Street.
The area
just east of Kasold Drive and between West 22nd Terrace and West 22nd
Street was raised as an area of concern by a landowner. There is an
apparent low spot that exists where storm water ponds at the rear lot lines of
the first three homes just east of Kasold Drive in this area. The City has agreed to further
investigate this as a portion of the roadway improvements. The
preliminary solution is to add area inlets in the backyards and connect this
system to the storm sewers along Kasold Drive.
Generally
speaking, the downstream systems that the proposed Kasold Drive storm sewers are connecting to will
be sufficient in size. Therefore, no significant downstream upgrades will
be necessary. However, there is one location north of Scioto Drive that will need to be checked
during the final design phase. The downstream data was not available
during this study phase to check the capacity of the existing system.
Therefore, the sizing of this system will need to be verified.
Figure D
shows a plan view of the existing layout for Kasold Drive between 15th Street and Clinton Parkway. The proposed storm sewer
inlets and pipes can be seen on this drawing.
OPTION 1 REMOVE &
REPLACE EXISTING PAVEMENT
Many
options were considered viable for the ultimate replacement of Kasold Drive from Clinton Parkway to 15th Street. One of the options
considered in this study is the removal and replacement of the existing
pavement without improving the roadway profile.
A design
speed of 45 mph was selected for all of the designs included in this
study. The existing and proposed posted speed will be 40 mph.
Figure E
shows the existing profile. The curves shown in red indicate the vertical
curves that are substandard for the design speed. The scope of this
option includes replacing the existing pavement, curb and gutter, and storm
sewers. The replacement of the existing pavement includes stabilized base
treatment, bound drainable base, and edge drains. A sidewalk/recreation
path will not be included in this option except in areas where a sidewalk
presently exists.
A couple
issues will need to be addressed even though the intention of this option is to
just replace the pavement. First, the existing pavement is crowned in the
middle of the southbound lanes and the northbound lanes. Therefore, storm
sewer inlets are necessary on both sides of the pavement. Bartlett &
West would propose removing the crown from the through lanes and replace the
section with a consistent cross slope from the median to the outside curb
line. This will eliminate the need for inlets on the median side, thus
reducing maintenance issue. Second, a portion of the existing grade
between Scioto Drive and Tam OShanter Drive is less than 1.0%, which is less
than normal City of Lawrence design criteria. Longitudinal street slopes less than 1.0% cause
problems with street drainage, and our design adjusts the street profile in
this area to achieve minimum desirable grade.
There
are advantages to the removal and replacement of the existing pavement.
Unfortunately, they are limited. The advantages include the following:
- Reduced construction costs
- Reduced construction
schedule
Both
these advantages go somewhat hand in hand. Of the four options discussed
in this study, the construction cost for this option is the cheapest at
$3,100,000 for the asphaltic pavement option and $3,327,000 for the concrete
option. The lesser cost is attractive when considering only the here and
now. In addition, the construction schedule will be the shortest of any
option due to the limited utility relocation and limited roadway improvements.
Choosing not to provide a
recreation path will reduce many of the projects obstacles, thus reducing the
time required for construction.
There
are several disadvantages to consider for this option. Some of the disadvantages
are related to not adjusting the roadway profile so that current engineering
design criteria can be met. Other disadvantages are related to project
amenities that will not be achievable due to existing conditions. The
disadvantages include the following:
- Poor sight distances on
vertical curves
- Steep tangent grades
- No left turn lanes
throughout much of the project
- Poor access through the
grass median
- Failure of the intersection
of Kasold Drive and Clinton Parkway
- Not providing pedestrian access
throughout the project
First,
almost all of the existing vertical curves are substandard for the entire
length of the project. There are presently 14 vertical curves along the
route. Of the 14 curves, only three of the vertical curves meet the
standard AASHTO design criteria for the design speed, none of which are crest
curves. A crest curve is one in which the driver is coming over the top
of a hill and needs sight distance to react to objects in the road so that
appropriate stopping or maneuvering can occur. If the design speed is
reduced to the posted speed, then 6 of the 14 curves are substandard, two of
which are crest vertical curves.
Second,
the existing 11.2% grade north of Augusta Drive is in excess of 10%, which is
the Citys maximum street grade
according to the design criteria. To complicate the issue, the AASHTO
criteria indicate that the appropriate maximum grade for an arterial street is
six to eight percent unless site issues prohibit this possibility. While
there are significant site issues, the profile can be improved to a certain
degree.
This
option does not include left turn bays to protect turning movements. With
present traffic at 20,000 vehicles per day and future traffic counts in excess
of 30,000 vehicles per day, safe travel becomes very difficult without refuge
for turning vehicles in the form of left turn lanes. The left turn
movement, unlike the right turn movement, often requires a driver to come to a
complete stop due to oncoming traffic. This stop condition in a through
lane results in many opportunities for conflict. Rear end accidents are
common in areas where vehicles come to a complete stop in a through lane.
Additionally,
the existing openings in the grass median create hazards for turning vehicles,
as well as through traffic. While the existing grass median is
aesthetically pleasing, the storage area in the median is not adequate for a
turning vehicle to remove itself from the through lanes. Therefore, these
openings add to the hazard of stopping in a through lane. Rear end
accidents are common at these locations.
Fifth,
the intersection of Kasold Drive and Clinton Parkway is already failing from a
traffic capacity standpoint. The traffic analysis that was completed
shows that all legs of this intersection are in poor condition. Not
surprisingly, the north leg is the intersection in the worst condition.
The Kasold Drive southbound traffic wanting to
turn eastbound onto Clinton Parkway is provided a very short left
turn only lane. However, this left turn only lane is short due to the
proximity of the West 22nd Terrace intersection. The short
left turn only lane causes vehicles turning left onto Clinton Parkway to stack up into the southbound
through lane even during off peak hours of the day. This is a dangerous
condition that will result in additional accidents as the traffic volumes
increase. The analysis shows that a dual left turn lane is necessary to
improve the efficiency of this portion of the intersection. The
improvement of this intersection is a key component to the overall success of
the Kasold Drive project.
Finally,
pedestrian access is a key benefit to living in Lawrence. There are sidewalks and
recreation paths throughout the City that are used by thousands of people on a
daily basis. The recreation paths are being connected through town so
that pedestrians and cyclists can have access to safe activity throughout the City of Lawrence. Removing and replacing
the existing pavement will not provide an opportunity to add sidewalks or
recreation paths to the project. There are a limited amount of sidewalks
along the existing route. Arterial streets are not meant for shared
access with pedestrians. Furthermore, the stretches of Kasold to the
north of 15th Street and south of Clinton Parkway offer sidewalks/recreation paths
on both sides of the street, so continuity becomes a real issue for this
project.
Construction Cost Opinion
As
mentioned previously, the construction cost opinion for this option is the
lowest of all options being considered. The construction cost opinion on
the following page provides information for both the asphaltic pavement option
and the concrete pavement option. The asphaltic pavement option includes
concrete pavement from Clinton Parkway to just north of Augusta Drive and from just south of Seminole Drive to 15th Street. Using concrete in these
areas is to compensate for the heavy amount of stopping and starting and
turning movements for car and truck traffic. The other cost issue that
needs to be accounted for is the relocation of the Citys waterlines, which the
Department of Utilities has estimated to cost $750,000.
OPTION 2 PREFERRED
PROFILE ALIGNMENT (10% GRADE)
The
profile for Kasold Drive was studied extensively to
address many of the sight distance issues that exist along the route.
Several variations of proposed profiles were considered to determine which
profile best fit the existing conditions. Ultimately, a profile was
developed that not only improves the existing conditions but reasonably fits
into the existing improvements. The only difference between Option 2 and
3 is the street profile north of Augusta Drive. For Option 2, the grade
north of Augusta Drive is 10 percent. The Option
2 profile is shown on Figure F.
The
following discussion summarizes the changes made to the existing street profile
that improve vehicular and pedestrian travel along the route. First, the
hill directly north of Clinton Parkway has been cut down approximately
two vertical feet to improve sight distance at the adjacent
intersections. This will benefit both directions so that southbound cars
approaching the Clinton Parkway intersection and northbound cars
approaching the West 22nd Terrace intersection can see vehicles at
those intersections from a greater distance, which will increase the overall
safety of these signalized intersections. Second, the two sag vertical
curves near West 22nd Street and the Quail Creek apartments have been
combined into one longer curve. Short, choppy curves produce an
undesirable effect on drivers. The single, longer vertical curve will
improve the feel of the roadway in this area. Third, the crest at the top
of the hill north of Augusta Drive will be cut down approximately
two vertical feet. In addition, this vertical curve will be almost
doubled in length and the grade on the south side of the crest will be reduced
from 11.2% to 10.0%. Both of these measures result in much improved sight
distance, making for a safer roadway. Fourth, the roller coaster area
between Tam OShanter and Seminole Drive will be softened. The top
of the middle hill will be reduced by approximately two vertical feet.
This solution will increase sight distances and improve the ride of the
roadway. Finally, the vertical curve just north of Seminole Drive will be reduced by approximately
one vertical foot. In addition, the grade just south of the top of this
hill will be reduced from 7.5% to 6.0%. This will minimize sight distance
issues coming into this hill.
This
option will be constructed according to the typical sections discussed
previously. This option also includes the construction of a 10 recreation
path adjacent to the new roadway. The recreation path will extend along
the entire route on the west side. In most instances, the recreation path
will be two feet from the back of curb.
There
are several advantages to this option. Many of these advantages are
engineering related, in addition to aesthetic items that will help improve the
roadway. The advantages of Option 2 are as follows:
- Improved sight distances on
vertical curves resulting in better safety
- Flatter tangent grades
resulting in better route continuity
- Center left turn lanes
provided for all minor intersections
- Appropriate intersection
geometrics for traffic volumes at signalized intersections
- Pedestrian access throughout
the entire length of the project
First, the
vertical curves have been improved along the route to meet the AASHTO design
criteria for a 45 mph design speed. The ultimate advantage to improving
the vertical curves is to provide added safety for the traveling public.
The vertical curves are improved by softening the grades into and out of the
curves, as well as increasing the curve length. These improvements
combine to provide a safer environment. Drivers in the through lanes are
able to see far enough in front of them that they are able to safely stop
and/or maneuver their vehicles, if necessary. This also assists drivers
trying to enter the roadway. For instance, this becomes especially
important in the areas where vehicles are entering and exiting the residential
home sites along the east side of Kasold Drive between Augusta Drive and Tam OShanter Drive. The improved vertical
curves also increase the safety at the signalized intersections. Being
able to see the oncoming intersections when approaching a signalized
intersection is of utmost importance for drivers in all situations.
Second,
reduced grades assist drivers with sight distances and make vertical curves
more gradual and easier to drive. The existing grades have been reduced
in almost every instance. The previous paragraph discussed the benefits
made to the vertical curves along the route. Perhaps the most important
tangent grade issue to discuss is the steep grade just north of Augusta Drive. The existing grade in
this area is 11.2%, and this option has reduced the grade to 10.0%. While
the 10% grade is not as flat as AASHTO design criteria dictates, it is an
appropriate grade when considering the surrounding existing conditions.
The 10.0% grade will require retaining walls within the existing
right-of-way. Figure F-1 shows a cross section for the location where the
tallest wall will be necessary. In addition, this figure also shows the
cross section 200 north and south of the tallest wall point. It is
important to note that the necessary wall height decreases rather quickly.
Furthermore,
a center turn lane has been proposed for all intersections. Traffic
volumes dictate that a turn lane is appropriate anywhere a left turn needs to
occur. The center turn lanes will be constructed from West 22nd Street to Augusta Drive and from Tam OShanter Drive to Seminole Drive.
Fourth,
the intersections at Clinton Parkway and 15th Street will be improved to make the
flow of traffic more efficient. The Clinton Parkway intersection will include seven
lanes at the north leg of the intersection. The southbound traffic will
have access to dual left turn lanes, two through lanes, and a right turn only
lane. Two through lanes will be constructed for the northbound
traffic. These improvements will repair an intersection that is presently
not able to handle the existing traffic. Next, the 15th Street intersection will be improved to
include a right turn only lane in addition to the existing lanes. There
are considerable right turn movements from northbound Kasold Drive to eastbound 15th Street.
Finally,
a 10 recreation path will be constructed along the west side of the entire
route. The path will connect existing sidewalks/recreation paths
throughout Lawrence to provide continuity of
pedestrian access. Presently, a 10 recreation path exists on the west
side of Kasold Drive south of Clinton Parkway. A sidewalk exists north
of 15th Street on the west side of Kasold Drive. Therefore, the proposed
recreation path for this project will connect sidewalks that presently do not
connect.
There
are some disadvantages for this option. Some of these items are a result
of advantages that are being provided to the project. While some items
are listed as disadvantages, there are also reasons provided to justify some of
the disadvantages. The disadvantages include the following:
- Steep grade north of Augusta Drive still questionable
- Retaining wall required for
recreation path construction
- Higher construction costs
- Longer construction schedule
First,
while the grade north of Augusta Drive has been improved from 11.2% to
10.0%, this still leaves a relatively steep grade through this stretch of Kasold Drive. AASHTO design guidelines
indicate that the maximum allowable grade for an arterial road should be
8%. There is flexibility in the criteria that will allow steeper grades
if existing conditions require such. In this case, reducing the grade to
something less than 10.0% will require significantly more retaining wall, which
will be shown in the discussion of Option 3.
Second,
retaining wall will be required along much of the project due to the recreation
path construction. Unfortunately, the construction of a retaining wall
for the recreation path is a necessary evil to the benefit of gaining the
recreation path. The retaining wall protects the existing landscaping and
fences in the yards along the west side of Kasold Drive. In addition to the
benefit of the recreation path, the retaining wall also eliminates the need for
additional right-of-way. So, ultimately, the cost of the retaining wall
is offset by two things. First, the retaining wall saves the real cost of
additional right-of-way if the wall was not constructed. Second, the wall
also allows the recreation path to be constructed. The recreation paths
value to the general public is very difficult to estimate.
Third,
the improved profile will cost more money for a few reasons. First, the
proposed profile will require additional earthwork. Second, as discussed
previously, the recreation path with the retaining wall will cost additional
project dollars. Again, the additional costs are providing additional
real value for the project, which is somewhat difficult to measure.
Fourth,
the additional amenities will require additional construction time. The
improved profile will require significant utility relocations. In
addition, the recreation path and retaining wall will require additional time
over the option of just removing and replacing the pavement. However,
similar to costs, the additional time required to construct the improved
profile, recreation path, and retaining wall is somewhat difficult to measure
against the value added by improved amenities.
Construction Cost Opinion
The
construction cost opinion on the following page provides information for both the
asphaltic pavement option and the concrete pavement option. The asphaltic
pavement option includes concrete pavement from Clinton Parkway to just north of Augusta Drive and from just south of Seminole Drive to 15th Street. Using concrete in these
areas is to compensate for the heavy amount of stopping and starting and
turning movements for car and truck traffic.
There
are a few other issues that may affect the costs for the project. First,
the Department of Utilities has determined that the waterlines along the
project need to be relocated as a part of the project. The Department of
Utilities has estimated that relocating the 6 and 12 waterlines will cost
approximately $750,000. Second, some easements will be required for
construction of this project to accommodate the new profile, recreation path,
and tie-in grades. The easements will be pedestrian and/or temporary
construction easements. Additional road right-of-way will not be
required. Although the easement limits have not been identified, a cost
of $50,000 is estimated for the purposes of this study. Finally, the City may need to pay for the
relocation or adjustment of some of the overhead power poles for the Westar
Energy facilities. These potential costs have not been identified, but
roughly are estimated to cost $40,000.
OPTION 3 PREFERRED PROFILE ALIGNMENT
(8% GRADE)
Much of
the discussion from Option 2 is applicable to the Option 3 discussion. Therefore,
many of the issues discussed under this option will be a repeat of the previous
discussion. However, any repetition of previous discussions is necessary
so the analysis of this option can be considered separately from the other
options.
The profile
for Kasold Drive was studied extensively to try
and address many of the sight distance issues that exist along the route.
Several variations of proposed profiles were considered to determine which
profile best fit the existing conditions. Ultimately, a profile was
developed that not only improves the existing conditions but reasonably fits
into the existing landscape. The only difference between Option 2 and 3
is the grade north of Augusta Drive. For Option 3, the grade
north of Augusta Drive is 8.0%. The Option 3
profile is shown on Figure G.
The
following discussion summarizes the changes to the existing profile to improve
vehicular and pedestrian travel along the route. First, the hill directly
north of Clinton Parkway has been cut down approximately
two vertical feet to improve sight distance at the adjacent
intersections. This will benefit both directions so that southbound cars
approaching the Clinton Parkway intersection and northbound cars
approaching the West 22nd Terrace intersection can see vehicles at
those intersections from a greater distance, which will increase the overall
safety of these signalized intersections. Second, the two sag vertical
curves near West 22nd Street and the Quail Creek apartments have been
combined into one longer curve. Short, choppy curves produce an
undesirable effect on drivers. The single, longer vertical curve will
improve the feel of the roadway in this area. Third, the crest curve at
the top of the hill north of Augusta Drive will be cut down approximately
seven vertical feet. In addition, this curve will be almost doubled in
length and the grade on the south side of the crest will be reduced from 11.2%
to 8.0%. Both of these measures result in much improved sight distance,
making for a safer roadway. Fourth, the roller coaster area between Tam
OShanter and Seminole Drive will be softened. The top
of the middle hill will be reduced by approximately two vertical feet.
This solution will increase sight distances and improve the ride of the roadway.
Finally, the vertical curve just north of Seminole Drive will be reduced by approximately
one vertical foot. In addition, the grade just south of the top of this
hill will be reduced from 7.5% to 6.0%. This will alleviate any sight
distance issues coming into this hill.
This
option will be constructed according to the typical sections discussed
previously. This option also includes the construction of a 10
recreation path adjacent to the new roadway. The recreation path will
extend along the entire route on the west side. In most instances, the
recreation path will be two feet from the back of curb.
There
are several advantages to this option. Many of these advantages are
engineering related, in addition to aesthetic items that will help improve the
roadway. The advantages for Option 3 are as follows:
- Improved sight distances on
vertical curves resulting in better safety
- Flatter tangent grades
resulting in better route continuity
- Center left turn lanes
provided for all minor intersections
- Appropriate intersection
geometrics for traffic volumes at signalized intersections
- Pedestrian access throughout
the entire length of the project
First,
the vertical curves have been improved along the route to meet the AASHTO
design criteria for a 45 mph design speed. The ultimate advantage to
improving the vertical curves is to provide added safety for the traveling
public. The vertical curves are improved by softening the grades into and
out of the curves, as well as increasing the curve length. These
improvements combine to provide a safer environment. Drivers in the
through lanes are able to see far enough in front of them that they are able to
safely stop and/or maneuver their vehicles, if necessary. This also
assists drivers trying to enter the roadway. For instance, this becomes
especially important in the areas where vehicles are entering and exiting the
residential home sites along the east side of Kasold Drive between Augusta Drive and Tam OShanter Drive. The improved vertical
curves also increase the safety at the signalized intersections. Being
able to see the oncoming intersections when approaching a signalized
intersection is of utmost importance for drivers in all situations.
Second, reduced
grades assist drivers with sight distances and make vertical curves more
gradual and easier to drive. The existing grades have been reduced in
almost every instance. The previous advantage discussed the benefits to
the vertical curves along the route. Perhaps the largest tangent grade
issue to discuss is the steep grade just north of Augusta Drive. The existing grade in
this area is 11.2%, and this option has reduced the grade to 8.0%. An
8.0% grade is at the upper limit of acceptable grades for arterial roadways
according to the AASHTO design criteria. The 8.0% grade will require
retaining walls to remain within the existing right-of-way. Figure G-1
shows a cross section for the location where the tallest wall will be
necessary. In addition, this figure also shows the cross section 200
north and south of the tallest wall point. When comparing these road
sections to the road sections referred to in Option 2, Figure F-1, it quickly
becomes obvious that there will be substantially more retaining wall required
for Option 3.
Furthermore,
a center turn lane has been proposed for all intersections. Traffic
volumes dictate that a turn lane is appropriate anywhere a left turn needs to
occur. The center turn lanes will be constructed from West 22nd Street to Augusta Drive and from Tam OShanter Drive to Seminole Drive.
Fourth,
the intersections at Clinton Parkway and 15th Street will be improved to make the
flow of traffic more efficient. The Clinton Parkway intersection will include seven
lanes at the north leg of the intersection. The southbound traffic will
have access to dual left turn lanes, two through lanes, and a right turn only
lane. Two through lanes will be constructed for the northbound
traffic. These improvements will repair an intersection that is presently
not able to handle the existing traffic. Next, the 15th Street intersection will be improved to
include a right turn only lane in addition to the existing lanes. There
are considerable right turn movements from northbound Kasold Drive to eastbound 15th Street.
Finally,
a 10 recreation path will be constructed along the west side of the entire
route. The path will connect existing sidewalks/recreation paths
throughout Lawrence to provide continuity of pedestrian
access. Presently, a 10 recreation path exists on the west side of Kasold Drive south of Clinton Parkway. A sidewalk exists north
of 15th Street on the west side of Kasold Drive. Therefore, the proposed
recreation path for this project will connect sidewalks that presently do not
connect.
There
are a few disadvantages for this option. Some of these items are a result
of advantages that are being provided to the project. While some items
are listed as disadvantages, there are also reasons provided to justify some of
the disadvantages. The disadvantages include the following:
- Extensive retaining wall
required for both sides of the roadway
- Higher construction costs
- Longer construction schedule
First,
retaining wall will be required along much of the project due to the recreation
path construction and the 8.0% grade. While the 10.0% grade of Option 2
requires retaining wall on the west side to complete the recreation path
construction, the 8.0% grade will require extensive retaining wall on both the
west side and east side of Kasold Drive to construct the proposed
roadway. On the west side, the retaining wall will be almost 13 feet
tall. On the east side, the retaining wall at this same point would be
approximately 7.5 feet tall. This section of roadway would feel much like
a tunnel to the drivers. The other complication to this section of the
profile is the sight distance available for the cars pulling out of the
driveways of the homes on the east side. Many of the sight lines would be
obstructed by the retaining walls. The only viable option to reduce the
retaining wall on the east side is to cut down the landscape berms and relocate
the Westar Energy power poles. The landscaping berm would be expensive
from a public relations perspective. The relocation of the power poles
would be expensive monetarily. Therefore, the only perceived possibility
for Option 3 would be to construct the additional retaining wall, so that the
existing landscape berms and power poles can remain in place as much as
reasonably possible. Unfortunately, building this amount of retaining
wall and/or removing and replacing the landscape berms and power poles becomes
an unrealistic option.
Second,
the improved profile will cost more money for a couple reasons. First,
the proposed profile will require additional earthwork. Second, as
discussed previously, the retaining walls will increase the costs
significantly.
Fourth,
the additional amenities will require additional construction time. The
improved profile will require significant utility relocations. In
addition, the recreation path and retaining walls will require additional time
over Options 1 and 2. In addition, the construction sequencing will
require additional time due to the grade differences. The larger the
vertical difference, the more difficult the construction and therefore the need
for more time.
Construction Cost Opinion
The
construction cost opinion on the following page provides information for both
the asphaltic pavement option and the concrete pavement option. The
asphaltic pavement option includes concrete pavement from Clinton Parkway to just north of Augusta Drive and from just south of Seminole Drive to 15th Street. Using concrete in these
areas is to compensate for the heavy amount of stopping and starting and
turning movements for car and truck traffic.
There
are a few other issues that may affect the costs for the project. First,
the Department of Utilities has determined that the waterlines along the
project need to be relocated as a part of the project. The Department of
Utilities has estimated that relocating the 6 and 12 waterlines will cost
approximately $750,000. Second, some easements will be required for
construction of this project to accommodate the new profile, recreation path,
and tie-in grades. The easements will be pedestrian and/or temporary
construction easements. Additional road right-of-way will not be
required. Although the easement limits have not been identified, a cost
of $50,000 is estimated for the purposes of this study. Finally, the City may need to pay for the
relocation or adjustment of some of the overhead power poles for the Westar
Energy facilities. These potential costs have not been identified, but
roughly are estimated to cost $40,000.
OPTION 4 PARTIAL
PREFERRED PROFILE (10% GRADE)
Much of
the discussion from Option 2 is applicable to the Option 4 discussion.
Therefore, many of the issues discussed under this option will be a repeat of the
Option 2 discussion. However, any repetition of previous discussions is
necessary so the analysis of this option can be considered separately from the
other options.
The
profile for Kasold Drive was studied extensively to try
and address many of the sight distance issues that exist along the route.
Several variations of proposed profiles were considered to determine which
profile best fit the existing conditions. Ultimately, a profile was
developed that not only improves the existing conditions but reasonably fits
into the existing landscape. The only difference between Option 2 and 4
is that Option 4 does not include the improvements between Clinton Parkway and West 22nd Street. Option 4 was developed to
reduce overall project costs while still improving the existing roadway and
amenities. The Option 4 profile is shown on Figure H.
The
following discussion summarizes the changes made to the existing street profile
that improve vehicular and pedestrian travel along the route. First, the
crest at the top of the hill north of Augusta Drive will be cut down approximately
two vertical feet. In addition, this vertical curve will be almost
doubled in length and the grade on the south side of the crest will be reduced
from 11.2% to 10.0%. Both of these measures result in much improved sight
distance, making for a safer roadway. Second, the roller coaster area
between Tam OShanter and Seminole Drive will be softened. The top
of the middle hill will be reduced by approximately two vertical feet.
This solution will increase sight distances and improve the ride of the
roadway. Finally, the vertical curve just north of Seminole Drive will be reduced by approximately
one vertical foot. In addition, the grade just south of the top of this
hill will be reduced from 7.5% to 6.0%. This will minimize sight distance
issues coming into this hill.
This
option will be constructed according to the typical sections discussed
previously. This option also includes the construction of a 10
recreation path adjacent to the new roadway. The recreation path will
extend along the entire route on the west side. In most instances, the
recreation path will be two feet from the back of curb.
There are
some benefits to this option. The advantages of Option 4 are as follows:
- Improved sight distances on
most of the vertical curves resulting in slightly better safety
- Flatter tangent grades
resulting in better route continuity
- Center left turn lanes provided
for all minor intersections
- Appropriate intersection
geometrics for traffic volumes at 15th Street
- Pedestrian access throughout
the entire length of the project
First,
the vertical curves have been improved along the portion of the route to be improved
to meet the AASHTO design criteria for a 45 mph design speed. The
ultimate advantage to improving the vertical curves is to provide added safety
for the traveling public. The vertical curves are improved by softening
the grades into and out of the curves, as well as increasing the curve
length. These improvements combine to provide a safer environment.
Drivers in the through lanes are able to see far enough in front of them that
they are able to safely stop and/or maneuver their vehicles, if necessary.
This also assists drivers trying to enter the roadway. For instance, this
becomes especially important in the areas where vehicles are entering and
exiting the residential home sites along the east side of Kasold Drive between Augusta Drive and Tam OShanter Drive.
Second,
reduced grades assist drivers with sight distances and make vertical curves
more gradual and easier to drive. The existing grades have been reduced
in almost every instance north of West 22nd Street. The previous paragraph discussed
the benefits made to the vertical curves along the route. Perhaps the
most important tangent grade issue to discuss is the steep grade just north of Augusta Drive. The existing grade in
this area is 11.2%, and this option has reduced the grade to 10.0%. While
the 10% grade is not as flat as AASHTO design criteria dictates, it is an
appropriate grade when considering the surrounding existing conditions.
The 10.0% grade will require retaining walls within the existing right-of-way.
The previously discussed Figure F-1, shows a cross section for the location
where the tallest wall will be necessary. In addition, this figure also
shows the cross section 200 north and south of the tallest wall point.
It is important to note that the necessary wall height decreases rather
quickly.
Furthermore,
a center turn lane has been proposed for all intersections north of West 22nd Street. Traffic volumes dictate
that a turn lane is appropriate anywhere a left turn needs to occur. The
center turn lanes will be constructed from West 22nd Street to Augusta Drive and from Tam OShanter Drive to Seminole Drive.
Fourth,
the intersection at 15th Street will be improved to make the
flow of traffic more efficient. The 15th Street intersection will be improved to
include a right turn only lane in addition to the existing lanes. There
are considerable right turn movements from northbound Kasold Drive to eastbound 15th Street.
Finally,
a 10 recreation path will be constructed along the west side of the entire route
north of West 22nd Street. The path will connect
existing sidewalks/recreation paths throughout Lawrence to provide continuity of
pedestrian access. Presently, a 10 recreation path exists on the west
side of Kasold Drive south of Clinton Parkway. A sidewalk exists north
of 15th Street on the west side of Kasold Drive. Therefore, the proposed
recreation path for this project will connect sidewalks that presently do not
connect.
There are
several disadvantages for this option. Some of these items are a result
of advantages that are being provided to the project. The disadvantages
include the following:
- Intersection of Clinton Parkway still in failing condition
- Steep grade north of Augusta Drive still questionable
- Retaining wall required for
recreation path construction
- Higher construction costs
- Longer construction schedule
First,
the hill directly north of Clinton Parkway will not be cut down like it
would in either Option 2 or 3. This vertical curve does not meet the
AASHTO design criteria. Second, the intersection geometrics of Clinton Parkway will not be improved. The
left turn lane already stacks up beyond the available left turn lane storage,
which is a hazardous condition. This leg of the intersection will need to
be improved very soon regardless of the fact that it will not be addressed with
this option. If this option is chosen and completed in 2005, then the
residents and traveling public will most likely react negatively when Kasold Drive goes back under construction
within 5 years to improve a portion of an intersection that should have been
improved with an adjacent previous project. These two issues combined
will ignore a very important part of this corridor that needs to be improved.
Second,
while the grade north of Augusta Drive has been improved from 11.2% to
10.0%, this still leaves a relatively steep grade through this stretch of Kasold Drive. AASHTO design guidelines
indicate that the maximum allowable grade for an arterial road should be
8%. There is flexibility in the criteria that will allow steeper grades
if existing conditions require such. In this case, reducing the grade to
something less than 10.0% will require significantly more retaining wall, which
was discussed as a part of Option 3.
Next,
retaining wall will be required along much of the project due to the recreation
path construction. Unfortunately, the construction of a retaining wall
for the recreation path is a necessary evil to the benefit of gaining the
recreation path. The retaining wall protects the existing landscaping and
fences in the yards along the west side of Kasold Drive. In addition to the
benefit of the recreation path, the retaining wall also eliminates the need for
additional right-of-way. So, ultimately, the cost of the retaining wall
is offset by two things. First, the retaining wall saves the real cost of
additional right-of-way if the wall was not constructed. Second, the wall
also allows the recreation path to be constructed. The recreation paths
value to the general public is very difficult to estimate.
Fourth,
the improved profile will cost more money for a few reasons. First, the
proposed profile will require additional earthwork. Second, as discussed
previously, the recreation path with the retaining wall will cost additional
project dollars. Again, the additional costs are providing additional
real value for the project, which is somewhat difficult to measure.
Finally,
the additional amenities will require additional construction time. The
improved profile will require significant utility relocations. In
addition, the recreation path and retaining wall will require additional time
over the option of just removing and replacing the pavement. However,
similar to costs, the additional time required to construct the improved
profile, recreation path, and retaining wall is somewhat difficult to measure
against the value added by improved amenities.
Construction Cost Opinion
The
construction cost opinion on the following page provides information for both
the asphaltic pavement option and the concrete pavement option. The
asphaltic pavement option includes concrete pavement from Clinton Parkway to just north of Augusta Drive and from just south of Seminole Drive to 15th Street. Using concrete in these
areas is to compensate for the heavy amount of stopping and starting and
turning movements for car and truck traffic.
There
are a few other issues that may affect the costs for the project. First,
the Department of Utilities has determined that the waterlines along the
project need to be relocated as a part of the project. The Department of
Utilities has estimated that relocating the 6 and 12 waterlines will cost
approximately $750,000. Second, some easements will be required for
construction of this project to accommodate the new profile, recreation path,
and tie-in grades. The easements will be pedestrian and/or temporary
construction easements. Additional road right-of-way will not be
required. Although the easement limits have not been identified, a cost
of $50,000 is estimated for the purposes of this study. Finally, the City may need to pay for the
relocation or adjustment of some of the overhead power poles for the Westar
Energy facilities. These potential costs have not been identified, but
roughly are estimated to cost $40,000.
CONSTRUCTION ISSUES
Construction issues for this project include constructing the project
in a manner that provides as little disruption to the existing traffic and
residents while completing the project in a timely fashion. The ensuing
discussion will uncover the issues required to create a reasonable traffic
control plan. This will be followed by scheduling issues based on the
proposed sequencing.
Construction Sequencing
A few
options were discussed as possibilities for completing the construction of this
project. Those options included closing the road for the entire length
until all construction is complete, completing the project one half at a time,
and closing the project in phases.
First,
closing the entire length of the project during construction to through traffic
during was considered as an option. The benefit to this option is that
the project could be completed in the shortest time frame possible. The
contractor could perform work along all stretches of the project, and in all
likelihood, should be able to complete the project within one construction
season. The biggest downside to closing the entire route until
construction is complete is finding an alternate route for 20,000 vehicles per
day. The closest arterials are Wakarusa, one and a half miles to the
west, and Iowa Street, one mile to the east. The
only other through routes between Clinton Parkway and 15th
Street are residential type roads, including Crossgate, which passes through
the parking lot of Alvamar Country Club, and Inverness Drive. In addition,
drivers could find their way from Clinton Parkway to 15th Street through the residential street
network of Alvamar Estates, which lies just to the west of Kasold Drive between Clinton Parkway and 15th Street. Using the residential streets
is not really an option for this amount of traffic. Detouring this amount
of traffic to Wakarusa and/or Iowa Street for an entire construction
season is probably not a reasonable alternative either.
Second,
completing the project one half at a time is a fairly common solution to
traffic control for major road projects. The benefit to completing the
road one half at a time is that the traffic can be carried through
construction. Therefore, some traffic will naturally find its way around
the project; however, much of the existing traffic will continue to use the
existing roadway. The difficulty in this type of construction really lies
at the intersections, especially those that are signalized. For instance,
if the southbound lanes of Kasold were closed for construction and traffic was
using the two northbound lanes then major issues would arise at Clinton Parkway. As discussed previously,
the left turn movements are very significant from southbound Kasold Drive onto eastbound Clinton Parkway. If there was only one
lane available to southbound traffic, then the left turn movements would back
up traffic for hundreds of feet. Even if signing was used to prevent left
turns at this intersection, drivers might ignore the signing and still make left
turns having an adverse impact on traffic. This scenario would require
constant patrolling by the police to ensure that traffic control signing was
being followed. Finally, this type of sequencing will create a longer
time frame than just completely closing the route.
Third,
the notion of closing the project in phases was considered. For instance,
maybe 15th Street to Tam OShanter would be closed, and then Tam
OShanter to West 22nd Street, and then West 22nd Street
to Clinton Parkway. The biggest
benefit to this type of sequencing is that it allows a contractor to work
uninterrupted in certain areas of the project making more efficient use of
time. However, there are a couple downsides to this type of
sequencing. The first downside was discussed in detail in the option
considering closing the entire route for construction. Detouring this
amount of traffic for the entire construction season is difficult. Closing Kasold in phases really
requires the majority of traffic to be detoured for the entire construction
season, because the contractor would be doing essentially the same thing as
closing the entire route throughout construction. The second difficulty
lies in utility relocations. Doing utility relocations a portion of the
project at a time is not efficient for the utilities and creates a delay each
time a new phase is begun. Most of the time the utilities need to be
moved before the road construction can occur. Finally, this type of
construction will probably be no more efficient than closing the road one half
at a time.
Based on
the three previous construction sequencing options, Bartlett & West is
proposing a fourth sequencing option, which is a combination of the three
previous options. This discussion is appropriate for any of the options chosen.
However, Option 4 may require some modifications to this sequencing plan.
This three phase sequencing plan has balanced the construction activities with
completing the project as quickly as possible. The general sequencing
plan is shown on Figure J.
Phase
1
To begin
the project, the north leg of the intersection of Kasold Drive and Clinton Parkway and the south leg of the
intersection of Kasold Drive and 15th Street will be closed completely.
Kasold Drive would be closed from Clinton Parkway to just south of
West 22nd Street and from just north of Seminole Drive to 15th
Street. The contractor would be given 10 to 14 weeks to complete the
construction of both these portions of the project. Traffic would be
detoured away from Kasold Drive during this portion of the
project.
This
solution provides several benefits. First, the contractor will be able to
work on the two most difficult portions of the project without having to handle
traffic through any of the signalized intersections. This will provide
time efficiencies for the project. Second, traffic will not have to be
carried through the major intersections at Clinton Parkway or 15th Street. This will eliminate the
danger of left turns at Clinton Parkway and finding a place to
transition traffic back to the existing roadway south of Clinton Parkway. In addition, this
eliminates the need to transition traffic back to the existing north of 15th Street, which would be a very difficult
endeavor due to the existing grass medians north of 15th Street. Third, temporary traffic
signals will not be necessary on the project. Instead, when the
signalized intersections are reopened, the new traffic signals are in place and
operational allowing the traffic to flow smoothly through these highly
congested areas. Fourth, access to the commercial areas will be
interrupted for as short a time frame as possible. If the option was
chosen to carry traffic through construction, then disruption at the entrances
to the retail areas would be for the whole construction season instead of just
for a few months. Finally, utility relocations in both these areas will
be minor, so the contractor would not be delayed during construction. In
addition, this would allow utility companies to work on relocating their
facilities in the middle portion of the project, so the contractor could begin
work immediately on Phase 2 when Phase 1 is finished.
This
solution does have one main disadvantage. Closing the intersections will
create a need to detour through traffic away from Kasold Drive. However, this detour
would be for a relatively short time frame, therefore reducing the negative
impact on the existing traffic.
Phase
2
After
Phase 1 is complete and reopened to traffic, the contractor would then proceed
with the project by closing the road one half at a time. Kasold Drive could now be opened for traffic,
allowing the return of traffic to Kasold Drive and easing the original burden
placed on Iowa Street and Wakarusa Drive.
Phase 2
will consist of the contractor closing the southbound lanes, moving traffic to
the northbound lanes, and reconstructing the west half of the project.
This side makes the most sense due to roadway geometrics. In addition,
the proposed profile needs to be constructed on the west side first so that
side road connections can be made before northbound traffic is moved
over. The contractor can more easily maintain the traffic on the
northbound lanes first. The reconstruction of the southbound lanes would
include the completion of the recreation path and the retaining wall, as well
as the reconstruction of the side roads. The Alvamar Estates residents
will have access from 15th Street or Clinton Parkway during this phase.
Phase
3
After
Phase 2 is complete, the contractor would then move traffic onto the southbound
lanes and reconstruct the northbound lanes, which should be the easiest part of
the project since there will not be any side road reconstruction to
complete. The only access issue is for the homes directly abutting Kasold Drive on the east side. The
contractor should be able to provide temporary access to each driveway through
the use of temporary access roads.
Construction Schedule Issues
The
Public Works Department has indicated that they would like to get this project
constructed in 2005. The project will need to be bid as early as possible
in 2005 for this schedule to be met.
Major
road projects almost always begin with the relocation of utilities, if
necessary. As discussed in the utilities section of this study, every
utility along the route will be impacted. Therefore, it will be vital to
get the utility companies involved as early as possible in the process to allow
them to move before major road construction occurs. SBC has indicated that they may need
as much as 6 months to relocate their facilities. This would include
their internal engineering time and actual construction process. As
mentioned previously, a meeting will be held with all utilities present shortly
after approval of this study from the City Commission. This meeting
will make all the utilities aware of the time critical nature of the project.
The road
construction alone will normally take the better part of a construction season
to complete. This is especially true considering the fact that this
project is one mile long. As an example, the OConnell Road project, which is only a three lane
roadway, will take at least 6 months of construction time, and it is slightly
shorter than this project.
Therefore,
the utilities will need to start working on relocations as soon as reasonably
possible. The proposed construction sequencing provides an additional
opportunity upfront to finish utility relocations. As mentioned earlier,
the areas between 15th Street and Seminole Street and between West 22nd Street and Clinton Parkway have minor utility issues.
Therefore, while the road contractors are working on those sections of the
project, the utility contractors can work in the middle of the project
finishing their relocations prior to Phase 2 construction beginning. In
addition to that time frame, the utility companies will have time prior to the
project being bid.
The
overall schedule of the project is a very aggressive time frame for the project
to be completed. The City can create a date certain contract for the
contractor. No matter how the contract is written, there are always the
unforeseen circumstances that may create scheduling difficulties. For
instance, a longer than usual winter, wetter than normal spring, or an early
winter in 2005, will all cause issues with the construction season. Other
unknown issues may occur during construction that cannot be seen ahead of time.
RECOMMENDATION
There
are countless ways to analyze improvements for this project. The key is
to assess what key factors are important for this section of roadway.
Some of the questions that need to be answered include the following:
- How many lanes are
necessary?
- How should utilities be
relocated?
- Should asphalt or concrete
be used?
- Are sidewalks necessary on
both sides of the roadway?
- How can a new road be built
and still protect the existing landscaping on the east side?
The
questions are numerous, and no particular item is any more important than the
other. The difficulty is how do you balance the necessary amenities with
all the factors to be considered.
To begin
the recommendation section, the pros and cons of each option will be
reviewed. Second, Bartlett & West has developed an option alternative
analysis matrix that considers seven factors that are deemed important to the
overall success of the project. Next, a project cost comparison matrix
for each option is provided. Finally, after considering the information
important to the project, a final recommendation will be made.
First,
each option offered its own benefits and disadvantages. For a couple of
the options, certain advantages created their own disadvantages. For
instance, an improved profile also resulted in additional retaining wall
construction. The following is a brief summary of the pros and cons of
each option.
Option
1 Remove and Replace Existing Pavement
The
advantages include:
- Reduced construction costs
- Reduced construction
schedule
The
disadvantages include:
- Poor sight distances on
vertical curves
- Steep tangent grades
- No left turn lanes
throughout much of the project
- Poor access through the
grass median
- Failure of the intersection
of Kasold Drive and Clinton Parkway
- Not providing pedestrian
access throughout the project
Option
2 Preferred Profile (10% Grade North of Augusta Drive)
The
advantages include:
- Improved sight distances on
vertical curves resulting in better safety
- Flatter tangent grades
resulting in better route continuity
- Center left turn lanes
provided for all minor intersections
- Appropriate intersection
geometrics for traffic volumes at signalized intersections
- Pedestrian access throughout
the entire length of the project
The
disadvantages include:
- Steep grade north of Augusta Drive still questionable
- Retaining wall required for
recreation path construction
- Higher construction costs
- Longer construction schedule
Option
3 Preferred Profile (8% Grade North of Augusta Drive)
The
advantages include:
- Improved sight distances on
vertical curves resulting in better safety
- Flatter tangent grades
resulting in better route continuity
- Center left turn lanes
provided for all minor intersections
- Appropriate intersection
geometrics for traffic volumes at signalized intersections
- Pedestrian access throughout
the entire length of the project
The disadvantages
include:
- Extensive retaining wall
required for both sides of the roadway
- Higher construction costs
- Longer construction schedule
Option
4 Partial Preferred Profile (10% Grade North of Augusta Drive)
The
advantages include:
- Improved sight distances on
most of the vertical curves resulting in slightly better safety
- Flatter tangent grades
resulting in better route continuity
- Center left turn lanes
provided for all minor intersections
- Appropriate intersection
geometrics for traffic volumes at 15th Street
- Pedestrian access throughout
the entire length of the project
The
disadvantages include:
- Intersection of Clinton Parkway still in failing condition
- Steep grade north of Augusta Drive still questionable
- Retaining wall required for
recreation path construction
- Higher construction costs
- Longer construction schedule
Second,
Bartlett & West developed an option alternative analysis matrix that
included seven of the important items that needed to be considered as a part of
the final solution. The seven key elements that have been identified are
safety, pedestrian access, aesthetics, route continuity, long-term maintenance,
its fit with existing conditions, and the operation of the intersections.
Each of the seven elements has been given a weighting factor based on its
importance to the project. Each element can than be broken down by a
range of scores. The sum of the weighting factors multiplied by the
points assigned for that element provide an overall score based on a total
possible point total of 100 points.
Each
option is shown on the alternative analysis matrix, and they are separated into
the asphaltic pavement option and the concrete pavement option. The
alternative analysis matrix, shown on the following page, shows that Option 2
and Option 3 have received significantly higher point totals than Options 1 and
Option 4.
Next, a
project cost matrix breaks the costs of the project into several groups.
The first five elements are related to the previously shown opinion of
construction costs that were discussed at the end of each option in the
Proposed Options section of the study. Additional items that include
approximate costs are utility relocations, potential easement costs, and
engineering fees. The project cost matrix is shown following the
alternative analysis matrix.
Finally,
reviewing the information from the pros and cons list and the matrices provides
a pretty definitive answer to the appropriate road that should be
constructed. While Option 2 and Option 3 ranked fairly closely in the
alternative analysis matrix, the pros and cons list differentiate the two
rather easily. The only real difference between Option 2 and Option 3 is
the difference in the street grade for the area north of Augusta Drive. The grade north of Augusta is 10% for Option 2 and 8% for
Option 3. While it would appear that the flatter grade would be
preferable, that is not the case. The 8% grade will require substantially
more retaining wall, which will create sight distance issues for the people
exiting the homes on the east side of Kasold Drive. In addition, the
extra wall and additional earthwork will increase the costs substantially for
the project without providing an equally offsetting improvements to the
roadway. Therefore, Option 2 is considered the preferred solution for the
project.