TABLE OF
I. Introduction
B. Purpose
B. Area Business and Resident Survey
D. Lawrence Planning Commission Update
III. Ultimate Land Use for Watershed
B. City Input
IV. Data Collection
B. Surveys
V. Internal Drainage System Analysis
B. Findings and Recommendations
1. System 1
2. System 2
3. System 3
4. System 4
5. System 5
6. System 6
7. System 7
8. System 8
9. System 9
10. System 10
11. System 11
12. System 12
D. Hydrologic and Hydraulic Analyses
A. Overview
1. General Project Information
2. Data and Model Development
3. Input Parameter Development
4. Naming
5. Hydrologic Methodology
6. Model
1. General Project Information
2. Data Sources
3. Input Parameter Development
4. Results
E. Alternatives for Future Development
1. Flood Reduction Alternatives
2. Future Hydraulic Drainage Improvements
3. Summary
VII. Kansas River Floodplain Analysis
A. Purpose
B. Results
1. General Project Information
2. Data Sources
3. Input Parameter Development
EXE
I. Introduction
The
The
North Lawrence Drainage Study was divided into two main focus areas. The
Internal System consists of the
II. Recommendations
A. Overall Watershed
Several alternatives were investigated in the overall North Lawrence Drainage Study watershed to reduce flood elevations, lessen impacts on the “Internal Drainage System” facilities, provide drainage in the event of high flows on the Kansas River, and assess the effects of development in the floodplain. The investigations led to the four major recommendations below. The first bullet item is the key to reducing the burden on the Internal System from areas beyond the existing city limits.
A cost summary with regard to these Watershed Analysis recommendations is shown in the table on the next page.

B. Internal System
Analyses
for the Internal Drainage System provided areas of concern throughout the
|
Prioritization of Internal Systems |
||
|
Link Name |
Excess Peak Flow |
Total Estimated |
|
(cfs) |
(dollars) |
|
|
S1-1 |
315 |
$9,163,000 |
|
S6-1 |
168 |
$3,994,000 |
|
S9-1 |
133 |
$1,132,000 |
|
S1L1-1 |
96 |
$333,000 |
|
S1L5-1 |
85 |
$235,000 |
|
S1L7-1 |
85 |
$59,000 |
|
S1L3-1 |
56 |
$187,000 |
|
S6L3-1 |
56 |
$195,000 |
|
S6L3-7D |
New pipes |
$181,000 |
|
S4-1 |
43 |
$60,000 |
|
S6L2-1 |
37 |
$5,000 |
|
S4L4-1 |
35 |
$53,000 |
|
S4L2-1 |
27 |
$36,000 |
|
S9L1-1 |
21 |
$7,000 |
|
S1L2-1 |
20 |
$240,000 |
|
S8-1 |
17 |
$115,000 |
|
S10L2-1 |
13 |
$4,000 |
|
S7-1 |
13 |
$38,000 |
|
S5-1 |
10 |
$56,000 |
|
S10-1 |
6 |
$106,000 |
|
S1L4-1 |
1 |
$7,000 |
|
S1L6-1 |
0 |
$0 |
|
S11-1 |
0 |
$0 |
|
S3-1 |
0 |
$0 |
|
S2-1 |
0 |
$0 |
|
S12-1 |
0 |
$0 |
|
Total |
|
$16,206,000 |
The flows calculated in the analysis of the internal system assume that the cutoff north of 24/40 Highway, as recommended by the Watershed Analysis, is in place. However, the costs in the table for the Internal System Analysis are independent of the costs for the Watershed Analysis improvement recommendations. By adding the total costs from each of the two summary tables, the estimated cost of all recommendations is approximately $41 million.
As with the overall watershed, a viable option within the internal system is land purchase. In areas that naturally drain to a low point, it is often advantageous to preserve the ponding area by purchasing the parcel of land. Those costs are included in several of the system costs in the table.
III. Background
A. Watershed Description
The
North Lawrence watershed is estimated to be 9,100 acres generally bordered by
the Kansas River levee on the south and the Mud
The Kansas River floodplain completely encompasses North Lawrence. The natural silt loam soils are highly permeable. However, increased development is replacing those soils with nearly impermeable clay material in certain areas. In addition, extremely mild slopes across the landform cause frequent ponding and roadway overtopping. Historically, North Lawrence has been an agricultural community with low density residential development. Pockets of commercial and industrial development now appear in areas of the watershed. While parts of North Lawrence will likely remain agricultural, the projected future land use in other areas will add more and more impervious surfaces.
B. Purpose
The
Lawrence-Douglas
Public comments relating to current drainage issues, proposed developments, long-range plans, and floodplain regulations are at the root of this study. The purpose of this study is to identify areas with flooding problems, analyze the major elements of the storm drainage system with respect to long-term land use, and recommend needed improvements to correct or prevent systems from flooding. By doing this, proposed developments and long-range plans will be influenced. At the same time, regulations can be conceptualized to avoid potential pitfalls.
The North Lawrence Drainage Study has several major components which work toward the generation of system requirements for stormwater conveyance and infrastructure in the ultimate buildout scenario. The following major tasks were included in the study:
Along with the recommended improvements, the magnitude of the costs required to implement them were assessed. It should be noted though, that detailed design of the projects recommended in this report is required to produce proper construction documents and accurate cost estimates for system components.
The main body of the project report is divided up into seven sections. Summaries of the various sections are detailed below. For a detailed description of the methods or results of each section, refer to the main report.
IV. Public Involvement
The
North Lawrence Drainage Study public involvement program was designed to
establish meaningful and useful dialogue between stakeholders, businesses,
residents in the area and the study team. A series of outreach efforts
were conducted to catalogue and assess the public’s concerns. Members of
the project team provided an overview of study activities and public input to
the Lawrence Planning
V. Ultimate Land Use for Watershed
To accomplish the goals of the North Lawrence Drainage Study, the ultimate land use condition had to be determined for the study area. The future land uses within the watershed will help determine where to focus the stormwater system improvements and provide better insight into heading off potential development problems. The project team conferred with the Public Works Department, the Planning Office, and the Utilities Department of Lawrence. Information was gathered with regard to current zoning, potential developments and long-range plans and was used to produce an ultimate watershed land use guide.
While the information gathered was used to create the Ultimate Build-Out map, it was not intended to dictate specific policies with regard to land use in the North Lawrence Drainage Area. However, certain policies could be inferred from the findings of this study. For instance, lot splits currently require a hydraulic study to determine impacts. Due to the extensive hydraulic studies detailed in this report, it would not be necessary for developers to conduct individual studies, as long as the general recommendations of this study are followed (i.e. conveyance needs to be maintained within the floodplain).
VI. Data
Several
field visits were made to the study area to observe drainage patterns, take
photographs and verify structure sizes and orientations. A significant
portion of the North Lawrence watershed was surveyed for this project.
This information was used in the development of computer models of the
watershed. Information from the field survey forms was entered into
GIS. The basis for the evaluation of the North Lawrence watershed is the
digital base maps developed by the
VII. Internal Drainage System Analysis
The
system of
Results of the hydrologic and hydraulic analyses for the set of 12 systems representing the existing stormwater infrastructure within North Lawrence identified many surcharge locations for the ultimate buildout condition.
Recommendations were determined for each conduit or channel in a system based on the analysis of the entire system. It should be noted that improvements are to generally be made in a downstream to upstream manner within the system, as there is no advantage trying to deliver more flow to a downstream component that cannot convey the existing flow. Overall costs for each system upgrade were estimated; however, for the purposes of prioritizing public improvements on a smaller scale, excess peak flow was determined for each main stem and each lateral draining to the main stem of the system.
VIII. Watershed Analysis
There
were three main goals for this portion of the study: to reduce the demand
on the 2nd Street Pump Station, to expel floodwater from the basin
during times of high water on the Kansas River, and to investigate the effects
of development in the floodplain. It is recommended that the drainage
from the area north of 24/40 Highway be cut off and the water pumped over the
levee. The recommendation for reducing the burden on the
The recommendation for future development in the watershed is to maintain the current conveyance levels in the 100-year floodplain. This will mean allowing no development in these areas that would reduce the capacity for floodplain storage, and may require the purchase of small parcels of land to set aside exclusively for ponding.
As the area develops, it will become necessary to provide emergency services to the homes and businesses that populate the area. This will require the improvement of the major roads in the area and significant improvement of the hydraulic structures which carry flow under the roads. With a more dense urban population, the roads should be raised to meet the current APWA criteria with regard to overtopping during the 100-year event. This will result in some significant increases in required flow capacity over the existing hydraulic structures.
IX. Kansas River Floodplain Analysis
The existing conditions FEMA hydraulic model was revised to assess the amount of flooding that would occur in the North Lawrence area in the event of a breach of the Kansas River levee system. A “most likely” breach location was determined for the purpose of this analysis. For the levee breech condition, a 100-year Kansas River event would result in flood levels 0 to 7 feet deep in the North Lawrence Watershed (refer to the exhibit titled Watershed Analysis – Kansas River Inundation in Section VII).
The
The North Lawrence watershed is estimated to be 9,100 acres generally bordered by the Kansas River levee on the west and south an